Eurofiber Datacenter NL Zuid-West 2

Eurofiber Datacenter NL Zuid-West 2 is an operational data center operated by Eurofiber in Steenbergen, Netherlands. Our footprint estimate of its power is about 3.2 MW.

Key facts

StatusOperational
OperatorEurofiber
Facility power3.2 MW (range 1.6 MW to 5.1 MW)
Estimate from building footprint, low confidence. Footprint estimate: about 2,633 m² building outline x 1 floor(s) x 1.2 kW/m².
GPU capacity if all AIabout 1,400 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Networks18 networks, 2 internet exchanges
PeeringDB.
Also known asEurofiber data center NL South-West 2
AddressDrukkerij 6
Coordinates51.58754, 4.30506
Websiteeurofibercloudinfra.com

Power and grid

Nearest high-voltage substation150 kV Dinteloord, 150 kV, 7.3 km away (TenneT)
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
Nearest 220 kV+ substation380 kV Rilland, 380 kV, 19.2 km away
HV substations within 10 km2
Power plants within 50 km13 GW in 95 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity254 g CO₂ per kWh (Netherlands, 2025)
Average of all power made in the area. Ember.
Grid power mixgas 34.9%, wind 25%, solar 21.1%, coal 7.1%, bioenergy 5.1%. Clean power: 54.2%
Industrial power priceEUR 0.139 per kWh (Netherlands, 2026-S1)
Non-household users with 20 to 70 GWh per year, without VAT. Eurostat.

Climate and water

Average temperature10.7 °C
NASA POWER, average of 2001 to 2025.
Highest temperature38 °C (2001 to 2025)
Cooling degree days98 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy3.03 kWh per m² per day
Wind at 50 m6.9 m/s average
Water stress todayLow - Medium (10-20%) (Netherlands)
Share of the local water supply that people already use. WRI Aqueduct 4.0, country level.
Water stress in 2050Low - Medium (10-20%)
Business-as-usual scenario.

Satellite view

Questions

How much power does Eurofiber Datacenter NL Zuid-West 2 use?

We estimate the facility power at about 3.2 MW. Estimate from building footprint, low confidence.

How close is Eurofiber Datacenter NL Zuid-West 2 to the power grid?

The nearest high-voltage substation in OpenStreetMap is 150 kV Dinteloord (150 kV), about 7.3 km away.

How clean is the power for Eurofiber Datacenter NL Zuid-West 2?

The grid in Netherlands emits about 254 g CO₂ per kWh (2025). Largest sources: gas 34.9%, wind 25%, solar 21.1%.

Who operates Eurofiber Datacenter NL Zuid-West 2?

Eurofiber.

Data centers near Steenbergen

More Eurofiber data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.