Keppel Genting Lane Campus is an operational data center operated by Keppel Data Centres in Geylang, Singapore. Our footprint estimate of its power is about 3.9 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Keppel Data Centres |
| Facility power | 3.9 MW (range 1.6 MW to 9.8 MW) Estimate from building footprint, low confidence. Footprint estimate: about 32,631 m² site outline x 0.12 kW per m² of land. |
| GPU capacity if all AI | about 1,700 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Also known as | Keppel DC Singapore 8 · Keppel DC Singapore 7 |
| Opened | 2024 |
| Coordinates | 1.32539, 103.87666 |
| Website | keppeldatacentres.com/locations/asia-pacific/singapore/keppel-dc-singapore-8 |
Power and grid
| Nearest high-voltage substation | Kallang Bahru Substation 230kV, 230 kV, 900 m away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 5 |
| Power plants within 50 km | 19 GW in 38 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 497 g CO₂ per kWh (Singapore, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 91.1%, bioenergy 2.8%, solar 2.7%, oil and other fossil 2.5%, coal 0.9%. Clean power: 5.5% |
Climate and water
| Average temperature | 27.1 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 33.9 °C (2001 to 2025) |
| Cooling degree days | 3,296 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.82 kWh per m² per day |
| Wind at 50 m | 4 m/s average |
| Water stress today | NoData (Singapore) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Keppel Genting Lane Campus use?
We estimate the facility power at about 3.9 MW. Estimate from building footprint, low confidence.
How close is Keppel Genting Lane Campus to the power grid?
The nearest high-voltage substation in OpenStreetMap is Kallang Bahru Substation 230kV (230 kV), about 900 m away.
How clean is the power for Keppel Genting Lane Campus?
The grid in Singapore emits about 497 g CO₂ per kWh (2025). Largest sources: gas 91.1%, bioenergy 2.8%, solar 2.7%.
Who operates Keppel Genting Lane Campus?
Keppel Data Centres.
Data centers near Geylang
- Starhub Data Center @ Kaki Bukit 1.5 km
- BDx SIN1 - Singapore 1.7 km · 15 MW
- STTGDC SIN5 1.9 km · 6.5 MW
- Ascenix Pte Ltd 2.0 km
- CapitaLand data center in Singapore 2.1 km · 40 MW
- Singtel Kim Chuan Telecommunications Centre 2.2 km
- Racks Central 2.2 km · 18 MW
- Global Switch Singapore 2.3 km · 44 MW
More Keppel Data Centres data centers
- Keppel Data Centres | Keppel DC Singapore 5 Singapore
- Keppel Data Centres | Keppel DC Sydney 1 Australia
- Keppel Data Centres | iSeek Data Centre Australia
- Keppel Data Centres | Keppel DC Singapore 2 Singapore
- Keppel Data Centres | Keppel DC Singapore 4 Singapore
- Keppel Data Centres | Keppel DC Singapore 1 Singapore
- Keppel Data Centres | Basis Bay Data Centre Malaysia
- Keppel Data Centres | Cardiff Data Centre United Kingdom
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.