Meta is an operational data center operated by Meta in Los Lunas, United States. Our footprint estimate of its power is about 70 MW. Likely chips: NVIDIA GPUs (some Meta MTIA) (guess).

Key facts

StatusOperational
OperatorMeta
Facility power70 MW (range 35 MW to 111 MW)
Estimate from building footprint, low confidence. Footprint estimate: about 58,073 m² building outline x 1 floor(s) x 1.2 kW/m².
AI chipsNVIDIA GPUs (some Meta MTIA)
Guess from the operator, not confirmed. Meta trains on NVIDIA GPUs and adds in-house MTIA chips for inference.
GPU capacity if all AIabout 30,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
AddressMessenger Loop NW 4250, 87031, Los Lunas
Coordinates34.82587, -106.77890

Power and grid

Nearest high-voltage substationDepot Substation, 115 kV, 800 m away (Meta)
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
Nearest 220 kV+ substationPajarito Substation, 345 kV, 20 km away
HV substations within 10 km5
UtilityContinental Divide El Coop INC (cooperative)
Electric retail service territory (HIFLD, US government).
Balancing authorityPNM
Nearest gas pipelineEl Paso Natural Gas Co, interstate pipeline, 17 km away
US Energy Information Administration pipeline map. Straight-line distance.
Power plants within 50 km1.9 GW in 27 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity347 g CO₂ per kWh (New Mexico, 2025)
Average of all power made in the area. Ember.
Grid power mixwind 35.7%, gas 26.4%, coal 20.5%, solar 17.4%. Clean power: 53.3%
Industrial power priceUSD 0.051 per kWh (New Mexico, August 2026)
Average price paid by industrial users in the state. EIA Electric Power Monthly.

Climate and water

Average temperature13.7 °C
NASA POWER, average of 2001 to 2025.
Highest temperature40.8 °C (2001 to 2025)
Cooling degree days781 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy5.53 kWh per m² per day
Wind at 50 m5 m/s average
Water stress todayExtremely High (>80%) (New Mexico)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050Extremely High (>80%)
Business-as-usual scenario.

Satellite view

Questions

How much power does Meta use?

We estimate the facility power at about 70 MW. Estimate from building footprint, low confidence.

What chips does Meta use?

No chips are reported. Based on the operator, the likely chips are NVIDIA GPUs (some Meta MTIA).

How close is Meta to the power grid?

The nearest high-voltage substation in OpenStreetMap is Depot Substation (115 kV), about 800 m away. The local utility is Continental Divide El Coop INC, in the PNM balancing area.

How clean is the power for Meta?

The grid in New Mexico emits about 347 g CO₂ per kWh (2025). Largest sources: wind 35.7%, gas 26.4%, coal 20.5%.

Who operates Meta?

Meta.

Data centers near Los Lunas

More Meta data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.