Meta Los Lunas is an operational data center that is still expanding, operated by Meta in Los Lunas, United States. Its power is about 147 MW, growing to about 273 MW by 2028-01. Epoch AI estimates about 134,000 H100-equivalent AI chips (B300).
Power demand is growing at this site
Key facts
| Status | Operational, expanding |
|---|---|
| Operator | Meta |
| Users | Meta |
| Facility power | 147 MW Reported (Epoch AI or owner data) |
| IT power | 118 MW |
| Planned power | 273 MW by 2028-01-01 Epoch AI timeline projection. |
| AI compute | 134,000 H100-equivalents → 869,000 planned |
| AI chips | B300 Reported (Epoch AI or owner data) |
| GPU capacity if all AI | about 66,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Capital cost | USD 4.5 billion → 8.3 billion planned Epoch AI estimate, 2025 USD. |
| Also known as | Meta |
| Address | 4250 Messenger Lp, Los Lunas, NM 87031 |
| Coordinates | 34.83016, -106.78383 |
Build timeline
| Date | Power | H100e | What the satellite images and filings show |
|---|---|---|---|
| 2024-07-24 | 0 | 0 | Land clearing starts for new building. |
| 2026-03-01 | 114 MW | 100,000 | Building 1 is operational, based on no construction activity around the shell and cooling equipment, and about 5 months passing after structural completion. |
| 2026-07-28 | 114 MW | 100,000 | Building 2 (a tent-like building) shell is complete, but we don't believe it's operational because there is unpaved ground, no cars parked right in front, the first tent buildings at Meta Prometheus took about 16 months (it's been 10 months for this building). North-west of Building 1, the outline of a building of similar dimensions and style to Meta Jeffersonville's Building 1 is visible, this is labeled as Building 3. West of Building 1 we see more land clearing for what could be a building similar to Meta Jeffersonville's Building 2. |
| 2026-10-26 | 147 MW | 134,000 | Building 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July. |
| 2028-01-01 (projected) | 273 MW | 869,000 | Building 3 is estimated to be operational. This is estimated from the timeline of similar buildings at other Meta sites. |
Source: Epoch AI Frontier Data Centers.
Chip deployments
| Date | Chip | Units | Basis |
|---|---|---|---|
| 2026-03-01 | B300 | 39,453 | Estimate |
| 2026-10-26 | B300 | 53,061 | Estimate |
| 2028-01-01 | B300 | 98,523 | Estimate |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Meta Los Lunas use?
Public data puts the facility power at about 147 MW, with about 273 MW planned by 2028. Reported (Epoch AI or owner data).
What chips does Meta Los Lunas use?
Reported chips: B300.
Who operates Meta Los Lunas?
Meta. Reported users: Meta.
Data centers near Los Lunas
- Meta 338 m · 87 MW
- Meta 496 m · 70 MW
- Meta Los Lunas Data Center 553 m
- Meta 656 m · 70 MW
- Meta 672 m · 87 MW
- Molina Healthcare 23.8 km · 4 MW
- ServerCondo-219 Albuquerque 30.8 km
- bigbyte.cc 30.8 km
More Meta data centers
- Meta Hyperion United States
- QTS Cedar Rapids United States
- Meta Prometheus United States
- Meta Bowling Green United States
- Meta Montgomery United States
- QTS Eagle Mountain United States
- Meta Huntsville Data Center United States
- Altoona Meta Data Center United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.