Key facts
| Status | Operational |
|---|---|
| Facility power | 18 MW (range 7.3 MW to 45 MW) Estimate from building footprint, low confidence. Footprint estimate: about 151,086 m² site outline x 0.12 kW per m² of land. |
| AI chips | NVIDIA GPUs (some Microsoft Maia) Guess from the operator, not confirmed. Microsoft AI capacity is mostly NVIDIA, with a few in-house Maia chips. |
| GPU capacity if all AI | about 7,700 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | 42.07694, -88.13389 |
Power and grid
| Utility | Commonwealth Edison Co (investor owned) Electric retail service territory (HIFLD, US government). |
|---|---|
| Balancing authority | PJM |
| Nearest gas pipeline | Northern Illinois Gas Co, intrastate pipeline, 1.5 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Grid carbon intensity | 247 g CO₂ per kWh (Illinois, 2025) Average of all power made in the area. Ember. |
| Grid power mix | nuclear 49.9%, gas 16.6%, coal 15.8%, wind 12.8%, solar 4.5%. Clean power: 67.3% |
| Industrial power price | USD 0.113 per kWh (Illinois, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 9.5 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 40.5 °C (2001 to 2025) |
| Cooling degree days | 465 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.67 kWh per m² per day |
| Wind at 50 m | 6.8 m/s average |
| Water stress today | Medium - High (20-40%) (Illinois) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Microsoft Data Center - Hoffman Estates use?
We estimate the facility power at about 18 MW. Estimate from building footprint, low confidence.
What chips does Microsoft Data Center - Hoffman Estates use?
No chips are reported. Based on the operator, the likely chips are NVIDIA GPUs (some Microsoft Maia).
How clean is the power for Microsoft Data Center - Hoffman Estates?
The grid in Illinois emits about 247 g CO₂ per kWh (2025). Largest sources: nuclear 49.9%, gas 16.6%, coal 15.8%.
Data centers near Hoffman Estates
- Aligned Data Center 13.3 km · 40 MW
- GigeNET CHI3 13.6 km
- RagingWire CH1 - NTT 14.0 km
- NTT Chicago CH3 14.4 km · 15 MW
- NTT Chicago CH4 14.5 km · 9.4 MW
- T5@Chicago 14.5 km · 14 MW
- Microsoft CHI12 Data Center 14.6 km · 13 MW
- Prime Data Centers 15.4 km · 11 MW