Multicoms Paris (Velizy)
Multicoms Paris (Velizy) is an operational data center operated by MULTICOMS FACILITIES MANAGEMENT in Paris, France. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | MULTICOMS FACILITIES MANAGEMENT |
| Networks | 1 networks PeeringDB. |
| Address | 6 Allée Latécoère |
| Coordinates | 48.78504, 2.20992 |
| Website | multicoms.net/content/view/12/58 |
Power and grid
| Nearest high-voltage substation | Robinson, 225 kV, 2.9 km away (SNCF Réseau) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 19 |
| Power plants within 50 km | 1.9 GW in 47 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 41 g CO₂ per kWh (France, 2025) Average of all power made in the area. Ember. |
| Grid power mix | nuclear 68.3%, hydro 10.3%, wind 8.8%, solar 5.6%, gas 3%. Clean power: 94.9% |
| Industrial power price | EUR 0.098 per kWh (France, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 10.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 38.2 °C (2001 to 2025) |
| Cooling degree days | 106 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.19 kWh per m² per day |
| Wind at 50 m | 6.4 m/s average |
| Water stress today | Low - Medium (10-20%) (France) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Multicoms Paris (Velizy) to the power grid?
The nearest high-voltage substation in OpenStreetMap is Robinson (225 kV), about 2.9 km away.
How clean is the power for Multicoms Paris (Velizy)?
The grid in France emits about 41 g CO₂ per kWh (2025). Largest sources: nuclear 68.3%, hydro 10.3%, wind 8.8%.
Who operates Multicoms Paris (Velizy)?
MULTICOMS FACILITIES MANAGEMENT.
Data centers near Paris
- dc2scale PAR3 (Vélizy-Villacoublay) 103 m · 0.8 MW
- Cogent Velizy 204 m
- Cogent Paris 2 237 m
- UltraEdge Velizy 296 m · 8.1 MW
- Datacenter Orange 658 m · 24 MW
- Equinix PA13X 666 m · 79 MW