OPCORE DC1
OPCORE DC1 is an operational data center operated by OPCORE in Bezons, France. Our footprint estimate of its power is about 12 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | OPCORE |
| Facility power | 12 MW (range 6.1 MW to 19 MW) Estimate from building footprint, low confidence. Footprint estimate: about 10,146 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 5,100 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | 48.92538, 2.22367 |
Power and grid
| Grid carbon intensity | 41 g CO₂ per kWh (France, 2025) Average of all power made in the area. Ember. |
|---|---|
| Grid power mix | nuclear 68.3%, hydro 10.3%, wind 8.8%, solar 5.6%, gas 3%. Clean power: 94.9% |
| Industrial power price | EUR 0.098 per kWh (France, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 10.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 38.2 °C (2001 to 2025) |
| Cooling degree days | 106 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.19 kWh per m² per day |
| Wind at 50 m | 6.4 m/s average |
| Water stress today | Low - Medium (10-20%) (France) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does OPCORE DC1 use?
We estimate the facility power at about 12 MW. Estimate from building footprint, low confidence.
How clean is the power for OPCORE DC1?
The grid in France emits about 41 g CO₂ per kWh (2025). Largest sources: nuclear 68.3%, hydro 10.3%, wind 8.8%.
Who operates OPCORE DC1?
OPCORE.
Data centers near Bezons
- Cogent Paris 2.4 km
- Groupe Cyllene - DC - Nanterre 2.5 km
- dc2scale Nanterre 3.1 km
- Telco Center 3.3 km
- Bouygues Télécom data center in Nanterre 3.4 km · 1.8 MW
- MENGINE 3.4 km
- Equinix PA7 - Paris, Energy Park 3.5 km · 13 MW
- UltraEdge Paris - Courbevoie 3.5 km
More OPCORE data centers
- OPCORE DC6-5 France
- OPCORE - DC3 / PAR3 France
- OPCORE DC6-2 France
- OPCORE DC6-6 France
- OPCORE - DC5 / PAR5 France
- OPCORE - DC2 / PAR2 France
- OPCORE - DC4 / PAR4 France
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.