Quebec 2k H100 Cluster
Quebec 2k H100 Cluster is an operational AI data center in Québec, Canada. Its power is about 2.8 MW. Epoch AI estimates about 2,000 H100-equivalent AI chips (NVIDIA H100 SXM5 80GB).
Key facts
| Status | Operational |
|---|---|
| Facility power | 2.8 MW Reported (Epoch AI or owner data) |
| AI compute | 2,000 H100-equivalents |
| AI chips | NVIDIA H100 SXM5 80GB Reported (Epoch AI or owner data) |
| Chip count | 2,000 Largest reported cluster at this site (Epoch AI). |
| GPU capacity if all AI | about 1,200 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | Quebec, Canada |
| Coordinates | 46.81219, -71.20279 |
Power and grid
| Nearest high-voltage substation | Poste de Limoilou, 235 kV, 2.5 km away (Hydro-Québec) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 7 |
| Power plants within 50 km | 55 MW in 4 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 192 g CO₂ per kWh (Canada, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 52.8%, gas 19.7%, nuclear 12.8%, wind 8%, coal 2.7%. Clean power: 76.5% |
Climate and water
| Average temperature | 3.1 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 29.3 °C (2001 to 2025) |
| Cooling degree days | 56 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.34 kWh per m² per day |
| Wind at 50 m | 5 m/s average |
| Water stress today | Low - Medium (10-20%) (Canada) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
GPU clusters at this site
| Cluster | Chips | Count | Power | Since |
|---|---|---|---|---|
| Quebec 2k H100 Cluster | NVIDIA H100 SXM5 80GB | 2,000 | 2.8 MW | 2025-01-14 |
Source: Epoch AI GPU Clusters.
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Quebec 2k H100 Cluster use?
Public data puts the facility power at about 2.8 MW. Reported (Epoch AI or owner data).
What chips does Quebec 2k H100 Cluster use?
Reported chips: NVIDIA H100 SXM5 80GB.
How close is Quebec 2k H100 Cluster to the power grid?
The nearest high-voltage substation in OpenStreetMap is Poste de Limoilou (235 kV), about 2.5 km away.
How clean is the power for Quebec 2k H100 Cluster?
The grid in Canada emits about 192 g CO₂ per kWh (2025). Largest sources: hydro 52.8%, gas 19.7%, nuclear 12.8%.
Data centers near Québec
- Data center in Québec 7.9 km · 46 MW
- Vantage Data Centers (QC2) 8.1 km · 14 MW
- Data center in L'Ancienne-Lorette 11.3 km · 24 MW
- QScale 17.8 km · 13 MW
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.