Smart City Telecom Maitland Colo
Smart City Telecom Maitland Colo is an operational data center operated by Smart City Telecom in Orlando, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Smart City Telecom |
| Address | 1101 N Keller Rd |
| Coordinates | 28.63882, -81.39965 |
| Website | smartcitytelecom.com/business/maitland-data-center-co-location |
Power and grid
| Nearest high-voltage substation | Trout Lake Substation, 230 kV, 2.3 km away (Duke Energy) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 8 |
| Utility | Reedy Creek Improvement Dist (municipal) Electric retail service territory (HIFLD, US government). |
| Balancing authority | FPC |
| Nearest gas pipeline | Florida Gas Trans Co, interstate pipeline, 7.4 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 7.4 GW in 18 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 436 g CO₂ per kWh (Florida, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 71.7%, nuclear 11.2%, solar 11.1%, coal 3.7%, bioenergy 1.2%. Clean power: 23.6% |
| Industrial power price | USD 0.089 per kWh (Florida, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 22.3 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 39.1 °C (2001 to 2025) |
| Cooling degree days | 1,919 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.87 kWh per m² per day |
| Wind at 50 m | 5.3 m/s average |
| Water stress today | High (40-80%) (Florida) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | High (40-80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Smart City Telecom Maitland Colo to the power grid?
The nearest high-voltage substation in OpenStreetMap is Trout Lake Substation (230 kV), about 2.3 km away. The local utility is Reedy Creek Improvement Dist, in the FPC balancing area.
How clean is the power for Smart City Telecom Maitland Colo?
The grid in Florida emits about 436 g CO₂ per kWh (2025). Largest sources: gas 71.7%, nuclear 11.2%, solar 11.1%.
Who operates Smart City Telecom Maitland Colo?
Smart City Telecom.
Data centers near Orlando
- Atlantic.net 2.4 km
- HostDime Orlando Data Center 2.4 km · 10 MW
- HostDime Orlando Tier IV Data Center 3.0 km
- Colo Solutions Downtown Orlando 11.8 km
- E-Foam 17.5 km · 1 MW
- CoreSite - Orlando (OR1) 23.6 km
- Data center in Polk City 57.3 km · 3.3 MW
- ACW Winter Haven 75.5 km
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.