Yellowstone Data Center
Yellowstone Data Center is an operational data center in Jakarta, Indonesia. Our footprint estimate of its power is about 44 MW.
Key facts
| Status | Operational |
|---|---|
| Facility power | 44 MW (range 22 MW to 71 MW) Estimate from building footprint, low confidence. Footprint estimate: about 6,160 m² building outline x 6 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 19,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | -6.21536, 106.83692 |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 150 kV, 900 m away (Perusahaan Listrik Negara) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Unnamed substation, 500 kV, 13.3 km away |
| HV substations within 10 km | 33 |
| Power plants within 50 km | 10 GW in 15 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 705 g CO₂ per kWh (Indonesia, 2025) Average of all power made in the area. Ember. |
| Grid power mix | coal 69.4%, gas 11.6%, hydro 6.7%, bioenergy 5.3%, other renewables 3.4%. Clean power: 15.8% |
Climate and water
| Average temperature | 27.3 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 34.2 °C (2001 to 2025) |
| Cooling degree days | 3,369 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 5.04 kWh per m² per day |
| Wind at 50 m | 3.9 m/s average |
| Water stress today | Medium - High (20-40%) (Indonesia) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Yellowstone Data Center use?
We estimate the facility power at about 44 MW. Estimate from building footprint, low confidence.
How close is Yellowstone Data Center to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (150 kV), about 900 m away.
How clean is the power for Yellowstone Data Center?
The grid in Indonesia emits about 705 g CO₂ per kWh (2025). Largest sources: coal 69.4%, gas 11.6%, hydro 6.7%.
Data centers near Jakarta
- EDGE2 (EG2) - Digital Edge JKT2 - Jakarta 250 m · 30 MW
- Matrix Data Center JK3 (MDC JK3) 625 m
- NEX Datacenter (NEX-JK1) Jakarta 1.3 km
- DCI Indonesia (E1) 1.4 km
- Biznet MegaPOP Jakarta MidPlaza 1.9 km
- PSN Networks 2.1 km
- NTT Indonesia Jakarta 2 2.2 km
- NTT Jakarta 1 Data Center (JKT1) 2.3 km