Data Center Directory

AWS Berwick

AWS Berwick is an operational data center that is still expanding, operated by Amazon Web Services in Berwick, United States. Its power is about 139 MW, growing to about 212 MW by 2027-08. Epoch AI estimates about 81,000 H100-equivalent AI chips (Trainium2).

Power demand is growing at this site

Key facts

StatusOperational, expanding
OperatorAmazon Web Services
UsersAnthropic (speculative)
ProjectProject Rainier
Facility power139 MW
Reported (Epoch AI or owner data)
IT power108 MW
Planned power212 MW by 2027-08-01
Epoch AI timeline projection.
AI compute81,000 H100-equivalents → 145,000 planned
AI chipsTrainium2
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 60,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 4.1 billion → 6.4 billion planned
Epoch AI estimate, 2025 USD.
Water use0.13 million gallons per day
Also known asAmazon AWS PHL
Address1125 Electron Ave, Berwick, PA 18603
Coordinates41.08385, -76.14353

Build timeline

DatePowerH100eWhat the satellite images and filings show
2021-07-0100Land clearing begins. [Talen Energy](https://www.datacenterdynamics.com/en/news/talen-energy-to-build-300mw-nuclear-powered-cryptomining-facility-and-data-center-in-us/) reported on July 12, 2021 that site-preparation permits had already been obtained and site work was underway, while permits for construction of the first building were still being pursued. We model land clearing as starting from the beginning of the month.
2023-01-1700[Cumulus](https://www.prnewswire.com/news-releases/cumulus-data-completes-key-milestones-in-construction-of-its-flagship-zero-carbon-susquehanna-data-center-campus-301722751.html) completes a 48 MW, 300,000 sq ft powered shell for the first data center at the Susquehanna campus. The shell is available for lease, with the campus still awaiting its first tenant and commercial operations.
2024-03-0400[AWS](https://www.sec.gov/Archives/edgar/data/1622536/000162828025023501/tln-20250331.htm) acquires the Cumulus/Talen building campus for $650M.
2024-06-0100Building 1 fit out and related construction begins under Amazon, based on the [Susquehanna River Basin Commission](https://www.srbc.gov/waav/search/GetPending?documentType=Application&isABRe=false&projectNumber=2024-056) (SRBC) schedule.
2025-09-0966 MW35,000Building 1 operational estimate. According to [Google Earth Satellite Imagery](https://earth.google.com/web/search/Berwick,+PA/@41.08459175,-76.14321499,203.05778839a,756.59305105d,35y,0h,0t,0r/data=CiwiJgokCYCDFkPTLDRAEX6DFkPTLDTAGUGoL_2-pEVAIRNn30rGL03AQgIIAUICCABKDQj___________8BEAA) from this date, Building 1 appears structurally complete and likely operational, while Building 2 is still missing two generators.
2026-01-07102 MW58,000Building 2 operational estimate. This is based on the progress visible in the September 2025 image. [The DEP](https://www.pacodeandbulletin.gov/secure/pabulletin/data/vol56/56-4/56-4.pdf) also issues an air plan approval to add 48 more emergency generators on this date.
2026-03-12102 MW58,000[The SRBC](https://www.srbc.gov/waav/Search/getdocket?documenttype=Approval&isabre=False&projectnumber=20260301) increases approved water use from 0.060 MGD to 0.129 MGD. This supports that some expansion is happening, but does not explicitly prove a third operational building.
2026-05-05102 MW58,000Buildings 1 and 2 visibly complete and operational. Building 3 appears complete and may be commissioning, but it's likely not operational yet given the immediate surrounding construction work. Several additional building shells and pads are still in construction, but none are assumed operational due to all the construction work visible. This is based on satellite imagery from this date.
2026-08-01139 MW81,000Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it. Basing MW estimate using Building 2 as a reference.
2027-08-01 (projected)212 MW145,000Building 4 expected to come online around August 2027, judging from prior satellite imagery. Modeled at twice Building 2's capacity because Building 4 is approximately twice its size.

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2025-09-09Trainium253,760Estimate
2026-01-07Trainium288,799Estimate
2026-08-01Trainium2123,838Estimate
2027-08-01Trainium350,055Estimate

Satellite view

Questions

How much power does AWS Berwick use?

Public data puts the facility power at about 139 MW, with about 212 MW planned by 2027. Reported (Epoch AI or owner data).

What chips does AWS Berwick use?

Reported chips: Trainium2.

Who operates AWS Berwick?

Amazon Web Services. Reported users: Anthropic.

Data centers near Berwick

More Amazon Web Services data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.