Amazon Ridgeland

Amazon Ridgeland is an operational data center that is still expanding, operated by Amazon Web Services in Mississippi, United States. Its power is about 273 MW, growing to about 1.0 GW by 2028-09. Epoch AI estimates about 171,000 H100-equivalent AI chips (Trainium2).

Power demand is growing at this site

Key facts

StatusOperational, expanding
OperatorAmazon Web Services
UsersAnthropic (speculative)
ProjectProject Rainier
Facility power273 MW
Reported (Epoch AI or owner data)
IT power228 MW
Planned power1.0 GW by 2028-09-29
Epoch AI timeline projection.
AI compute171,000 H100-equivalents → 788,000 planned
AI chipsTrainium2
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 130,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 8.6 billion → 31.8 billion planned
Epoch AI estimate, 2025 USD.
Energy partnersEntergy
Address1626 County Line Road Ridgeland, Mississippi
Coordinates32.40003, -90.19717

Build timeline

DatePowerH100eWhat the satellite images and filings show
2024-02-2400Land clearing begins
2025-10-0400Roof complete on Buildings 3
2026-05-15273 MW171,000Buildings 1-4 are operational, based on the buildings shells and backup generators and most of the landscaping looking complete. Building 5 roof is complete but still lacks cooling equipment.
2027-02-09 (projected)341 MW214,000Building 5 is operational (estimate).
2028-09-29 (projected)1.0 GW788,000Buildings 6-14 are operational (estimate). Buildings 1-4 took an estimated 2.25 years on this site. We assume Buildings 6-14 get underway by July 2026, and take the same time as Buildings 1-4. This is later than the [expected completion by 2027](https://www.datacenterdynamics.com/en/news/aws-confirmed-as-company-behind-10bn-mississippi-data-center-development/).

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2026-05-15Trainium2261,244Estimate
2028-09-29Trainium3502,392Estimate

Satellite view

Questions

How much power does Amazon Ridgeland use?

Public data puts the facility power at about 273 MW, with about 1.0 GW planned by 2028. Reported (Epoch AI or owner data).

What chips does Amazon Ridgeland use?

Reported chips: Trainium2.

Who operates Amazon Ridgeland?

Amazon Web Services. Reported users: Anthropic.

Data centers near Mississippi

More Amazon Web Services data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.