AWS Ridgeland Data Center
AWS Ridgeland Data Center is an operational data center operated by Amazon Web Services in Ridgeland, United States. Our footprint estimate of its power is about 151 MW. Likely chips: AWS Trainium and NVIDIA GPUs (guess).
Key facts
| Status | Operational |
|---|---|
| Operator | Amazon Web Services |
| Facility power | 151 MW (range 60 MW to 378 MW) Estimate from building footprint, low confidence. Footprint estimate: about 1,259,263 m² site outline x 0.12 kW per m² of land. |
| AI chips | AWS Trainium and NVIDIA GPUs Guess from the operator, not confirmed. AWS deploys its own Trainium chips next to NVIDIA GPUs. |
| GPU capacity if all AI | about 65,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | 32.40754, -90.18825 |
Power and grid
| Utility | Entergy Mississippi LLC (investor owned) Electric retail service territory (HIFLD, US government). |
|---|---|
| Balancing authority | MISO |
| Nearest gas pipeline | Gulf South Pipeline Co, interstate pipeline, 200 m away US Energy Information Administration pipeline map. Straight-line distance. |
| Grid carbon intensity | 454 g CO₂ per kWh (Mississippi, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 73.9%, nuclear 14.7%, coal 5.3%, solar 3.7%, bioenergy 1.7%. Clean power: 20.8% |
| Industrial power price | USD 0.076 per kWh (Mississippi, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 18 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 41.3 °C (2001 to 2025) |
| Cooling degree days | 1,329 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.58 kWh per m² per day |
| Wind at 50 m | 4.4 m/s average |
| Water stress today | Low - Medium (10-20%) (Mississippi) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does AWS Ridgeland Data Center use?
We estimate the facility power at about 151 MW. Estimate from building footprint, low confidence.
What chips does AWS Ridgeland Data Center use?
No chips are reported. Based on the operator, the likely chips are AWS Trainium and NVIDIA GPUs.
How clean is the power for AWS Ridgeland Data Center?
The grid in Mississippi emits about 454 g CO₂ per kWh (2025). Largest sources: gas 73.9%, nuclear 14.7%, coal 5.3%.
Who operates AWS Ridgeland Data Center?
Amazon Web Services.
Data centers near Ridgeland
- Amazon Web Services 503 m · 19 MW
- Amazon Web Services 615 m · 19 MW
- Amazon Ridgeland 1.2 km · 273 MW
- Data center in Canton 22.4 km · 19 MW
- Data center in Canton 22.6 km · 19 MW
- Data center in Canton 22.6 km · 19 MW
- Data center in Canton 22.7 km · 19 MW
- AWS Canton Data Center 22.9 km · 253 MW
More Amazon Web Services data centers
- Anthropic-Amazon New Carlisle United States
- Amazon Ridgeland United States
- Amazon Madison Mega Site United States
- AWS New Albany United States
- AWS Canton Data Center United States
- AWS Berwick United States
- AWS Umatilla Data Center United States
- Amazon Web Services United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.