Bouygues Telecom data center in Cabriès
Bouygues Telecom data center in Cabriès is an operational data center operated by Bouygues Telecom in Cabriès, France. Our footprint estimate of its power is about 3.8 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Bouygues Telecom |
| Facility power | 3.8 MW (range 1.9 MW to 6.1 MW) Estimate from building footprint, low confidence. Footprint estimate: about 1,053 m² building outline x 3 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 1,600 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | 43.48775, 5.35748 |
Power and grid
| Nearest high-voltage substation | Poste électrique de La Duranne, 225 kV, 300 m away (RTE) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 4 |
| Power plants within 50 km | 3.4 GW in 64 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 41 g CO₂ per kWh (France, 2025) Average of all power made in the area. Ember. |
| Grid power mix | nuclear 68.3%, hydro 10.3%, wind 8.8%, solar 5.6%, gas 3%. Clean power: 94.9% |
| Industrial power price | EUR 0.098 per kWh (France, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 14.2 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 41 °C (2001 to 2025) |
| Cooling degree days | 591 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.44 kWh per m² per day |
| Wind at 50 m | 6.1 m/s average |
| Water stress today | Low - Medium (10-20%) (France) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Bouygues Telecom data center in Cabriès use?
We estimate the facility power at about 3.8 MW. Estimate from building footprint, low confidence.
How close is Bouygues Telecom data center in Cabriès to the power grid?
The nearest high-voltage substation in OpenStreetMap is Poste électrique de La Duranne (225 kV), about 300 m away.
How clean is the power for Bouygues Telecom data center in Cabriès?
The grid in France emits about 41 g CO₂ per kWh (2025). Largest sources: nuclear 68.3%, hydro 10.3%, wind 8.8%.
Who operates Bouygues Telecom data center in Cabriès?
Bouygues Telecom.
Data centers near Cabriès
- TDF Datacenter Aix Marseille 4.0 km · 3.7 MW
- FDJ data center in Vitrolles 9.4 km
- Free Pro - Datacenter Marseille (MAR02) 14.2 km · 7.8 MW
- Free Pro - Marseille - MRS1 14.3 km
- EXA Edge DC Marseille 16.1 km · 2.2 MW
- Verizon Marseille 16.5 km · 1.1 MW
- Digital Realty MRS3 16.6 km · 32 MW
- Datacenter Sud 17.4 km
More Bouygues Telecom data centers
- Datacenter Bouygues Télécom France
- Datacenter Bouygues Télécom France
- Bouygues Télécom data center in Montpellier France
- Bouygues Télécom data center in Poitiers France
- Bouygues Télécom data center in Toulouse France
- Bouygues Télécom data center in Léognan France
- Bouygues Télécom data center in Nanterre France
- Bouygues Télécom data center in Tours France
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.