BVTNORXB - Beaverton Central Office
BVTNORXB - Beaverton Central Office is an operational data center operated by Ziply Fiber in Beaverton, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Ziply Fiber |
| Networks | 1 networks PeeringDB. |
| Address | 4155 SW Cedar Hills Blvd |
| Coordinates | 45.49018, -122.81164 |
| Website | ziplyfiber.com/wholesale/data-centers/colocation |
Power and grid
| Nearest high-voltage substation | Beaverton Substation, 115 kV, 1.3 km away (Portland General Electric) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Saint Mary's Substation, 230 kV, 3.2 km away |
| HV substations within 10 km | 21 |
| Utility | Portland General Electric Co (investor owned) Electric retail service territory (HIFLD, US government). |
| Balancing authority | PGE |
| Nearest gas pipeline | Northwest Pipeline, interstate pipeline, 14.5 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 947 MW in 58 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 200 g CO₂ per kWh (Oregon, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 44.6%, gas 33.9%, wind 14.5%, solar 5.2%, bioenergy 1.6%. Clean power: 66.2% |
| Industrial power price | USD 0.087 per kWh (Oregon, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 10 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 39.3 °C (2001 to 2025) |
| Cooling degree days | 79 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.67 kWh per m² per day |
| Wind at 50 m | 4 m/s average |
| Water stress today | Low - Medium (10-20%) (Oregon) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is BVTNORXB - Beaverton Central Office to the power grid?
The nearest high-voltage substation in OpenStreetMap is Beaverton Substation (115 kV), about 1.3 km away. The local utility is Portland General Electric Co, in the PGE balancing area.
How clean is the power for BVTNORXB - Beaverton Central Office?
The grid in Oregon emits about 200 g CO₂ per kWh (2025). Largest sources: hydro 44.6%, gas 33.9%, wind 14.5%.
Who operates BVTNORXB - Beaverton Central Office?
Ziply Fiber.
Data centers near Beaverton
- Digital Fortress (PTL2) 3.1 km
- Data Center 6.4 km · 2.7 MW
- SMRWORXA - Somerset West Central Office 7.6 km
- TGRDORXA - Tigard Central Office 7.9 km
- Verizon Hillsboro (Tanasbourne) Data Center 8.2 km · 8.8 MW
- Oracle 8.9 km · 6.4 MW
- Digital Realty Portland - PDX10 8.9 km · 8.9 MW
- TGN Hillsboro 9.0 km · 2.6 MW
More Ziply Fiber data centers
- BOTHWAXB - Bothell Central Office United States
- CRALIDXX - Coeur d'Alene Central Office United States
- EVRTWAXA - Everett Primary Central Office United States
- GRHMORXB - Gresham Central Office United States
- HLBOORXH - Hawthorne Central Office United States
- KNWCWAXA - Kennewick Central Office United States
- SMRWORXA - Somerset West Central Office United States
- TGRDORXA - Tigard Central Office United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.