Data Center Directory

TGRDORXA - Tigard Central Office

TGRDORXA - Tigard Central Office is an operational data center operated by Ziply Fiber in Tigard, United States. No power figure is public for this site yet.

Key facts

StatusOperational
OperatorZiply Fiber
Networks1 networks
PeeringDB.
Address8840 SW Burnham St
Coordinates45.42558, -122.76857
Websiteziplyfiber.com/wholesale/data-centers/colocation

Power and grid

Nearest high-voltage substationTigard Substation, 115 kV, 900 m away (Portland General Electric)
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
Nearest 220 kV+ substationMurrayhill Substation, 230 kV, 5.1 km away
HV substations within 10 km22
UtilityPortland General Electric Co (investor owned)
Electric retail service territory (HIFLD, US government).
Balancing authorityPGE
Nearest gas pipelineNorthwest Pipeline, interstate pipeline, 21.2 km away
US Energy Information Administration pipeline map. Straight-line distance.
Power plants within 50 km964 MW in 61 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity200 g CO₂ per kWh (Oregon, 2025)
Average of all power made in the area. Ember.
Grid power mixhydro 44.6%, gas 33.9%, wind 14.5%, solar 5.2%, bioenergy 1.6%. Clean power: 66.2%
Industrial power priceUSD 0.087 per kWh (Oregon, August 2026)
Average price paid by industrial users in the state. EIA Electric Power Monthly.

Climate and water

Average temperature10 °C
NASA POWER, average of 2001 to 2025.
Highest temperature39.3 °C (2001 to 2025)
Cooling degree days79 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy3.67 kWh per m² per day
Wind at 50 m4 m/s average
Water stress todayLow - Medium (10-20%) (Oregon)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050Low - Medium (10-20%)
Business-as-usual scenario.

Satellite view

Questions

How close is TGRDORXA - Tigard Central Office to the power grid?

The nearest high-voltage substation in OpenStreetMap is Tigard Substation (115 kV), about 900 m away. The local utility is Portland General Electric Co, in the PGE balancing area.

How clean is the power for TGRDORXA - Tigard Central Office?

The grid in Oregon emits about 200 g CO₂ per kWh (2025). Largest sources: hydro 44.6%, gas 33.9%, wind 14.5%.

Who operates TGRDORXA - Tigard Central Office?

Ziply Fiber.

Data centers near Tigard

More Ziply Fiber data centers

Sources

Correct this page or get the data