TGRDORXA - Tigard Central Office
TGRDORXA - Tigard Central Office is an operational data center operated by Ziply Fiber in Tigard, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Ziply Fiber |
| Networks | 1 networks PeeringDB. |
| Address | 8840 SW Burnham St |
| Coordinates | 45.42558, -122.76857 |
| Website | ziplyfiber.com/wholesale/data-centers/colocation |
Power and grid
| Nearest high-voltage substation | Tigard Substation, 115 kV, 900 m away (Portland General Electric) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Murrayhill Substation, 230 kV, 5.1 km away |
| HV substations within 10 km | 22 |
| Utility | Portland General Electric Co (investor owned) Electric retail service territory (HIFLD, US government). |
| Balancing authority | PGE |
| Nearest gas pipeline | Northwest Pipeline, interstate pipeline, 21.2 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 964 MW in 61 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 200 g CO₂ per kWh (Oregon, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 44.6%, gas 33.9%, wind 14.5%, solar 5.2%, bioenergy 1.6%. Clean power: 66.2% |
| Industrial power price | USD 0.087 per kWh (Oregon, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 10 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 39.3 °C (2001 to 2025) |
| Cooling degree days | 79 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.67 kWh per m² per day |
| Wind at 50 m | 4 m/s average |
| Water stress today | Low - Medium (10-20%) (Oregon) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is TGRDORXA - Tigard Central Office to the power grid?
The nearest high-voltage substation in OpenStreetMap is Tigard Substation (115 kV), about 900 m away. The local utility is Portland General Electric Co, in the PGE balancing area.
How clean is the power for TGRDORXA - Tigard Central Office?
The grid in Oregon emits about 200 g CO₂ per kWh (2025). Largest sources: hydro 44.6%, gas 33.9%, wind 14.5%.
Who operates TGRDORXA - Tigard Central Office?
Ziply Fiber.
Data centers near Tigard
- Digital Fortress (PTL2) 5.7 km
- BVTNORXB - Beaverton Central Office 7.9 km
- Siemens EDA - HDC / Data Center 11.9 km · 2.5 MW
- Digital Fortress (PTL) 12.6 km
- PTOR1 12.7 km · 12 MW
- Corepacket PDX-1 12.7 km
- Opus Interactive Portland (PDX01) 12.7 km
- LightPoint Corporation 12.8 km
More Ziply Fiber data centers
- BOTHWAXB - Bothell Central Office United States
- BVTNORXB - Beaverton Central Office United States
- CRALIDXX - Coeur d'Alene Central Office United States
- EVRTWAXA - Everett Primary Central Office United States
- GRHMORXB - Gresham Central Office United States
- HLBOORXH - Hawthorne Central Office United States
- KNWCWAXA - Kennewick Central Office United States
- SMRWORXA - Somerset West Central Office United States
Sources
Correct this page or get the data