Digital Realty data center in Sterling
Digital Realty data center in Sterling is an operational data center operated by Digital Realty in Sterling, United States. Our footprint estimate of its power is about 42 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Digital Realty |
| Facility power | 42 MW (range 21 MW to 67 MW) Estimate from building footprint, low confidence. Footprint estimate: about 34,902 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 18,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | Efficiency Drive 43715, 20166, Sterling |
| Coordinates | 38.95999, -77.48865 |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 230 kV, 600 m away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 52 |
| Utility | Northern Virginia Elec Coop (cooperative) Electric retail service territory (HIFLD, US government). |
| Balancing authority | PJM |
| Nearest gas pipeline | Dominion Transmission Co, interstate pipeline, 3.1 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 1.6 GW in 39 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 357 g CO₂ per kWh (Virginia, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 56.7%, nuclear 26.4%, solar 9.5%, coal 3.4%, bioenergy 3.3%. Clean power: 39% |
| Industrial power price | USD 0.100 per kWh (Virginia, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 12.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 40.7 °C (2001 to 2025) |
| Cooling degree days | 729 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.98 kWh per m² per day |
| Wind at 50 m | 5.3 m/s average |
| Water stress today | Medium - High (20-40%) (Virginia) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Digital Realty data center in Sterling use?
We estimate the facility power at about 42 MW. Estimate from building footprint, low confidence.
How close is Digital Realty data center in Sterling to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (230 kV), about 600 m away. The local utility is Northern Virginia Elec Coop, in the PJM balancing area.
How clean is the power for Digital Realty data center in Sterling?
The grid in Virginia emits about 357 g CO₂ per kWh (2025). Largest sources: gas 56.7%, nuclear 26.4%, solar 9.5%.
Who operates Digital Realty data center in Sterling?
Digital Realty.
Data centers near Sterling
- Digital Realty IAD44 259 m · 104 MW
- Amazon Web Services data center in South Riding 851 m · 21 MW
- CyrusOne NVA9 1.2 km · 15 MW
- CyrusOne Sterling NVA9 1.5 km · 49 MW
- Amazon IAD-180 2.4 km · 24 MW
- Amazon Fadeley III 3.1 km · 22 MW
- Google Data Center 3.7 km · 45 MW
- Tech Park at Brambleton 3.9 km · 27 MW
More Digital Realty data centers
- Digital Realty CH1 - Chicago United States
- Digital Realty IAD39 United States
- Digital Realty IAD51 United States
- Digital Realty IAD44 United States
- Digital Realty IAD41 United States
- Digital Realty Singapore SIN11 Singapore
- Digital Realty Toronto YYZ11 Canada
- Digital Realty IAD43 United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.