Energynet Datacenter
Energynet Datacenter is an operational data center operated by Hopkinsville Electric System in Hopkinsville, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Hopkinsville Electric System |
| Networks | 4 networks PeeringDB. |
| Address | 1820 E 9th St |
| Coordinates | 36.84784, -87.46516 |
| Website | hop-electric.com/internet |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 161 kV, 1 km away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Montgomery Substation, 500 kV, 34 km away |
| HV substations within 10 km | 5 |
| Utility | City Of Hopkinsville (municipal) Electric retail service territory (HIFLD, US government). |
| Balancing authority | TVA |
| Nearest gas pipeline | Texas Gas Transmission Co, interstate pipeline, 31.5 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 183 MW in 5 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 769 g CO₂ per kWh (Kentucky, 2025) Average of all power made in the area. Ember. |
| Grid power mix | coal 65.8%, gas 25.8%, hydro 5.3%, solar 2.4%, bioenergy 0.5%. Clean power: 8.2% |
| Industrial power price | USD 0.074 per kWh (Kentucky, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 14.2 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 42.3 °C (2001 to 2025) |
| Cooling degree days | 877 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.19 kWh per m² per day |
| Wind at 50 m | 5.2 m/s average |
| Water stress today | Low - Medium (10-20%) (Kentucky) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Energynet Datacenter to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (161 kV), about 1 km away. The local utility is City Of Hopkinsville, in the TVA balancing area.
How clean is the power for Energynet Datacenter?
The grid in Kentucky emits about 769 g CO₂ per kWh (2025). Largest sources: coal 65.8%, gas 25.8%, hydro 5.3%.
Who operates Energynet Datacenter?
Hopkinsville Electric System.
Data centers near Hopkinsville
- Google Montgomery Data Center 30.5 km · 309 MW
- Google 30.8 km · 38 MW
- SPC4A 31.0 km · 38 MW
- Russellvile EPB Smartnet 51.5 km
- Dynamics Mining 57.7 km · 4.7 MW
- Verizon Wireless 86.7 km · 2.8 MW
- Tennessee Processing Center LLC 93.0 km · 8.6 MW
- Level(3) Nashville (9th Ave) 94.1 km
Sources
Correct this page or get the data