G42 Artemis is an operational AI data center operated by G42 in Abu Dhabi, United Arab Emirates. Its power is about 1.2 MW. Epoch AI estimates about 82 H100-equivalent AI chips (NVIDIA V100).

Key facts

StatusOperational
OperatorG42
Facility power1.2 MW
Reported (Epoch AI or owner data)
AI compute82 H100-equivalents
AI chipsNVIDIA V100
Reported (Epoch AI or owner data)
Chip count1,296
Largest reported cluster at this site (Epoch AI).
GPU capacity if all AIabout 520 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
AddressAbu Dhabi, United Arab Emirates
Coordinates24.45352, 54.37744

Power and grid

Nearest high-voltage substationAl Quram substation, 400 kV, 2.9 km away
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
HV substations within 10 km20
Power plants within 50 km8.9 GW in 9 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity470 g CO₂ per kWh (United Arab Emirates, 2025)
Average of all power made in the area. Ember.
Grid power mixgas 68%, nuclear 21.2%, solar 9.9%. Clean power: 31.6%

Climate and water

Average temperature28.2 °C
NASA POWER, average of 2001 to 2025.
Highest temperature44 °C (2001 to 2025)
Cooling degree days3,739 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy5.88 kWh per m² per day
Wind at 50 m4.6 m/s average
Water stress todayExtremely High (>80%) (Abu Dhabi)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050Extremely High (>80%)
Business-as-usual scenario.

GPU clusters at this site

ClusterChipsCountPowerSince
G42 ArtemisNVIDIA V1001,2961.2 MW2019-11-01

Source: Epoch AI GPU Clusters.

Satellite view

Questions

How much power does G42 Artemis use?

Public data puts the facility power at about 1.2 MW. Reported (Epoch AI or owner data).

What chips does G42 Artemis use?

Reported chips: NVIDIA V100.

How close is G42 Artemis to the power grid?

The nearest high-voltage substation in OpenStreetMap is Al Quram substation (400 kV), about 2.9 km away.

How clean is the power for G42 Artemis?

The grid in United Arab Emirates emits about 470 g CO₂ per kWh (2025). Largest sources: gas 68%, nuclear 21.2%, solar 9.9%.

Who operates G42 Artemis?

G42.

Data centers near Abu Dhabi

More G42 data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.