Interxion PAR4 is an operational data center operated by Digital Realty in Nanterre, France. Our footprint estimate of its power is about 3 MW.

Key facts

StatusOperational
OperatorDigital Realty
Facility power3 MW (range 1.5 MW to 4.7 MW)
Estimate from building footprint, low confidence. Footprint estimate: about 1,234 m² building outline x 2 floor(s) x 1.2 kW/m².
GPU capacity if all AIabout 1,300 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
AddressRue du Port 21, 92000, Nanterre
Coordinates48.89395, 2.17506

Power and grid

Nearest high-voltage substationPoste électrique de Rueil, 225 kV, 600 m away (RTE)
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
HV substations within 10 km23
Power plants within 50 km2.1 GW in 50 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity41 g CO₂ per kWh (France, 2025)
Average of all power made in the area. Ember.
Grid power mixnuclear 68.3%, hydro 10.3%, wind 8.8%, solar 5.6%, gas 3%. Clean power: 94.9%
Industrial power priceEUR 0.098 per kWh (France, 2026-S1)
Non-household users with 20 to 70 GWh per year, without VAT. Eurostat.

Climate and water

Average temperature10.8 °C
NASA POWER, average of 2001 to 2025.
Highest temperature38.2 °C (2001 to 2025)
Cooling degree days106 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy3.19 kWh per m² per day
Wind at 50 m6.4 m/s average
Water stress todayLow - Medium (10-20%) (France)
Share of the local water supply that people already use. WRI Aqueduct 4.0, country level.
Water stress in 2050Medium - High (20-40%)
Business-as-usual scenario.

Satellite view

Questions

How much power does Interxion PAR4 use?

We estimate the facility power at about 3 MW. Estimate from building footprint, low confidence.

How close is Interxion PAR4 to the power grid?

The nearest high-voltage substation in OpenStreetMap is Poste électrique de Rueil (225 kV), about 600 m away.

How clean is the power for Interxion PAR4?

The grid in France emits about 41 g CO₂ per kWh (2025). Largest sources: nuclear 68.3%, hydro 10.3%, wind 8.8%.

Who operates Interxion PAR4?

Digital Realty.

Data centers near Nanterre