Mozoilo AJVP
Mozoilo AJVP is an operational data center operated by Mozoilo in Galdakao, Spain. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Mozoilo |
| Address | 48960, Galdakao |
| Coordinates | 43.24204, -2.87427 |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 132 kV, 800 m away (Iberdrola) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Subestación de Sidenor, 220 kV, 2.2 km away |
| HV substations within 10 km | 11 |
| Power plants within 50 km | 2.0 GW in 4 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 154 g CO₂ per kWh (Spain, 2025) Average of all power made in the area. Ember. |
| Grid power mix | solar 21.9%, gas 21.5%, wind 20.4%, nuclear 18.8%, hydro 11.4%. Clean power: 74.6% |
| Industrial power price | EUR 0.105 per kWh (Spain, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 11.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 36.9 °C (2001 to 2025) |
| Cooling degree days | 156 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.65 kWh per m² per day |
| Wind at 50 m | 5.5 m/s average |
| Water stress today | High (40-80%) (Spain) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Extremely High (>80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Mozoilo AJVP to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (132 kV), about 800 m away.
How clean is the power for Mozoilo AJVP?
The grid in Spain emits about 154 g CO₂ per kWh (2025). Largest sources: solar 21.9%, gas 21.5%, wind 20.4%.
Who operates Mozoilo AJVP?
Mozoilo.
Data centers near Galdakao
- EXA Edge DC Basauri 1.6 km
- Telxius Derio DC 6.1 km
- Data center in Zamudio 6.3 km · 2.2 MW
- Data center in Miranda de Ebro 60.4 km
- Data Center 2 Bilbao Arasur 60.5 km · 61 MW
- MERLIN Edged BIL03 - Bilbao-Arasur 60.5 km · 36 MW
- Ibercom San Sebastian 70.3 km
Sources
Correct this page or get the data