OptimumHQ is an operational data center in Mesa, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Also known as | The Chatfield Group |
| Address | South Val Vista Drive 1955, 85206, Mesa |
| Coordinates | 33.38041, -111.75267 |
Power and grid
| Utility | City Of Mesa (municipal) Electric retail service territory (HIFLD, US government). |
|---|---|
| Balancing authority | WALC |
| Nearest gas pipeline | El Paso Natural Gas Co, interstate pipeline, 3.4 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Grid carbon intensity | 311 g CO₂ per kWh (Arizona, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 43%, nuclear 25.6%, solar 17.5%, coal 7.5%, hydro 4.1%. Clean power: 49.8% |
| Industrial power price | USD 0.097 per kWh (Arizona, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 22.4 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 48.6 °C (2001 to 2025) |
| Cooling degree days | 2,283 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 5.8 kWh per m² per day |
| Wind at 50 m | 4.4 m/s average |
| Water stress today | Extremely High (>80%) (Arizona) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Extremely High (>80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How clean is the power for OptimumHQ?
The grid in Arizona emits about 311 g CO₂ per kWh (2025). Largest sources: gas 43%, nuclear 25.6%, solar 17.5%.
Data centers near Mesa
- Alliance Technology 2.3 km
- US Signal AZ01 - Phoenix 7.4 km
- Google Data Center 7.7 km · 76 MW
- Google Mesa 8.3 km · 237 MW
- GoDaddy - Gilbert 8.3 km · 8.6 MW
- All About Serving Process Server 8.6 km
- StrongMind 9.2 km · 1.9 MW
- EdgeConneX PHX02 Data Center 10.3 km · 56 MW