US Signal AZ01 - Phoenix
US Signal AZ01 - Phoenix is an operational data center operated by OneNeck IT Solutions in Gilbert, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | OneNeck IT Solutions |
| Networks | 3 networks PeeringDB. |
| Address | 1655 W Sunrise Blvd |
| Coordinates | 33.35517, -111.82682 |
| Website | ussignal.com |
Power and grid
| Nearest high-voltage substation | Corbell Substation, 230 kV, 400 m away (Salt River Project) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 3 |
| Utility | City Of Mesa (municipal) Electric retail service territory (HIFLD, US government). |
| Balancing authority | WALC |
| Nearest gas pipeline | El Paso Natural Gas Co, interstate pipeline, 500 m away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 5.5 GW in 25 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 311 g CO₂ per kWh (Arizona, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 43%, nuclear 25.6%, solar 17.5%, coal 7.5%, hydro 4.1%. Clean power: 49.8% |
| Industrial power price | USD 0.097 per kWh (Arizona, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 22.4 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 48.6 °C (2001 to 2025) |
| Cooling degree days | 2,283 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 5.8 kWh per m² per day |
| Wind at 50 m | 4.4 m/s average |
| Water stress today | Extremely High (>80%) (Arizona) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Extremely High (>80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is US Signal AZ01 - Phoenix to the power grid?
The nearest high-voltage substation in OpenStreetMap is Corbell Substation (230 kV), about 400 m away. The local utility is City Of Mesa, in the WALC balancing area.
How clean is the power for US Signal AZ01 - Phoenix?
The grid in Arizona emits about 311 g CO₂ per kWh (2025). Largest sources: gas 43%, nuclear 25.6%, solar 17.5%.
Who operates US Signal AZ01 - Phoenix?
OneNeck IT Solutions.
Data centers near Gilbert
- GoDaddy - Gilbert 1.4 km · 8.6 MW
- StrongMind 1.9 km · 1.9 MW
- All About Serving Process Server 4.2 km
- Emailage 5.9 km
- Google Mesa 6.7 km · 237 MW
- Digital Realty Data Center 6.8 km · 12 MW
- OptimumHQ 7.4 km
- Centersquare Phoenix (PHX3) 7.9 km · 7.6 MW
More OneNeck IT Solutions data centers
- US Signal OR01 - Bend United States
- US Signal CO01 - Denver United States
- US Signal IA01 - Des Moines United States
- US Signal MN01 - Minneapolis United States
- US Signal WI02 - Madison United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.