Princeton Digital JC3
Princeton Digital JC3 is an operational data center operated by Princeton Digital in Cikarang, Indonesia. Our footprint estimate of its power is about 14 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Princeton Digital |
| Facility power | 14 MW (range 7 MW to 22 MW) Estimate from building footprint, low confidence. Footprint estimate: about 11,609 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 6,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | -6.37467, 107.19029 |
Power and grid
| Nearest high-voltage substation | Gardu Induk Data Center, 150 kV, 200 m away (PLN) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | GITET Cibatu, 500 kV, 3.1 km away |
| HV substations within 10 km | 11 |
| Power plants within 50 km | 10 GW in 23 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 705 g CO₂ per kWh (Indonesia, 2025) Average of all power made in the area. Ember. |
| Grid power mix | coal 69.4%, gas 11.6%, hydro 6.7%, bioenergy 5.3%, other renewables 3.4%. Clean power: 15.8% |
Climate and water
| Average temperature | 24.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 35.3 °C (2001 to 2025) |
| Cooling degree days | 2,507 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 5.01 kWh per m² per day |
| Wind at 50 m | 3.1 m/s average |
| Water stress today | Medium - High (20-40%) (Indonesia) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Princeton Digital JC3 use?
We estimate the facility power at about 14 MW. Estimate from building footprint, low confidence.
How close is Princeton Digital JC3 to the power grid?
The nearest high-voltage substation in OpenStreetMap is Gardu Induk Data Center (150 kV), about 200 m away.
How clean is the power for Princeton Digital JC3?
The grid in Indonesia emits about 705 g CO₂ per kWh (2025). Largest sources: coal 69.4%, gas 11.6%, hydro 6.7%.
Who operates Princeton Digital JC3?
Princeton Digital.
Data centers near Cikarang
- Microsoft JKT05 386 m · 14 MW
- Amazon Web Services 423 m · 9.6 MW
- Digital Hyperspace Jakarta 533 m · 6.7 MW
- DIgital Edge CGK Campus 1.0 km
- STT Jakarta 1 1.2 km · 22 MW
- STTGDC JKT1 1.2 km
- Hyperscale Data Center (HDC) 1.3 km
- GTN Data Center 4.1 km · 6 MW
More Princeton Digital data centers
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.