365 Data Centers Alpharetta (GA1) is an operational data center operated by 365 Data Centers in Alpharetta, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | 365 Data Centers |
| Networks | 1 networks, 1 internet exchanges PeeringDB. |
| Address | 11650 Great Oaks Way |
| Coordinates | 34.06343, -84.27273 |
| Website | 365datacenters.com/alpharetta-data-center |
Power and grid
| Nearest high-voltage substation | Kimball Bridge Substation, 230 kV, 700 m away (Georgia Power) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 15 |
| Utility | Georgia Power Co (investor owned) Electric retail service territory (HIFLD, US government). |
| Balancing authority | SOCO |
| Nearest gas pipeline | Transcontinental Gas PL, interstate pipeline, 21.5 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 3.1 GW in 9 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 352 g CO₂ per kWh (Georgia, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 38.7%, nuclear 34.8%, coal 13.6%, solar 8.1%, bioenergy 3.2%. Clean power: 47.6% |
| Industrial power price | USD 0.131 per kWh (Georgia, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 16.1 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 42.1 °C (2001 to 2025) |
| Cooling degree days | 1,020 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.43 kWh per m² per day |
| Wind at 50 m | 4.5 m/s average |
| Water stress today | Medium - High (20-40%) (Georgia) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is 365 Data Centers Alpharetta (GA1) to the power grid?
The nearest high-voltage substation in OpenStreetMap is Kimball Bridge Substation (230 kV), about 700 m away. The local utility is Georgia Power Co, in the SOCO balancing area.
How clean is the power for 365 Data Centers Alpharetta (GA1)?
The grid in Georgia emits about 352 g CO₂ per kWh (2025). Largest sources: gas 38.7%, nuclear 34.8%, coal 13.6%.
Who operates 365 Data Centers Alpharetta (GA1)?
365 Data Centers.
Data centers near Alpharetta
- Data center in Alpharetta 296 m · 2.8 MW
- Ascent - Atlanta Data Center 705 m · 7.8 MW
- T5 Data Center 1.6 km · 12 MW
- Hewlett-Packard 2.1 km · 18 MW
- Flexential - Atlanta/Alpharetta (ATL3/4) 3.2 km · 9.7 MW
- Secure Data Center 3.9 km · 34 MW
- Strategic Datasphere 4.9 km · 41 MW
- Mapletree Industrial 4.9 km · 22 MW
More 365 Data Centers data centers
- 365 Data Centers Bridgewater (BW1) United States
- 365 Data Centers Aurora (CO1) United States
- 365 Data Centers Carlstadt (NJ3) United States
- 365 Data Centers Chicago (CH6) United States
- 365 Data Centers Commack (CNY) United States
- 365 Data Centers Detroit (DT1) United States
- 365 Data Centers Ft. Lauderdale (FLL) United States
- 365 Data Centers Herndon (VA1) United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.