Crown Castle Manchester (1 Sundial Ave) is an operational data center operated by Crown Castle in Manchester, United States. No power figure is public for this site yet.

Key facts

StatusOperational
OperatorCrown Castle
Networks1 networks
PeeringDB.
Address1 Sundial Ave
Coordinates42.97261, -71.46947
Websitefiber.crowncastle.com/solutions/infrastructure/colocation

Power and grid

Nearest high-voltage substationBedford Substation, 115 kV, 3.2 km away (Eversource)
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
Nearest 220 kV+ substationGranite Ridge Substation, 230 kV, 8.4 km away
HV substations within 10 km8
UtilityLiberty Utilities (Granite State Electri (investor owned)
Electric retail service territory (HIFLD, US government).
Balancing authorityISNE
Nearest gas pipelineEnergyNorth Nat Gas Co, interstate pipeline, 1.7 km away
US Energy Information Administration pipeline map. Straight-line distance.
Power plants within 50 km1.2 GW in 58 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity180 g CO₂ per kWh (New Hampshire, 2025)
Average of all power made in the area. Ember.
Grid power mixnuclear 55.3%, gas 27%, hydro 6.9%, bioenergy 4.1%, wind 2.4%. Clean power: 70.7%
Industrial power priceUSD 0.173 per kWh (New Hampshire, August 2026)
Average price paid by industrial users in the state. EIA Electric Power Monthly.

Climate and water

Average temperature8.6 °C
NASA POWER, average of 2001 to 2025.
Highest temperature37.9 °C (2001 to 2025)
Cooling degree days297 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy3.71 kWh per m² per day
Wind at 50 m4.5 m/s average
Water stress todayLow - Medium (10-20%) (New Hampshire)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050Low - Medium (10-20%)
Business-as-usual scenario.

Satellite view

Questions

How close is Crown Castle Manchester (1 Sundial Ave) to the power grid?

The nearest high-voltage substation in OpenStreetMap is Bedford Substation (115 kV), about 3.2 km away. The local utility is Liberty Utilities (Granite State Electri, in the ISNE balancing area.

How clean is the power for Crown Castle Manchester (1 Sundial Ave)?

The grid in New Hampshire emits about 180 g CO₂ per kWh (2025). Largest sources: nuclear 55.3%, gas 27%, hydro 6.9%.

Who operates Crown Castle Manchester (1 Sundial Ave)?

Crown Castle.

Data centers near Manchester

More Crown Castle data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.