Databank Houston Galleria (HOU5)
Databank Houston Galleria (HOU5) is an operational data center operated by DataBank in Houston, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | DataBank |
| Networks | 8 networks, 2 internet exchanges PeeringDB. |
| Address | 4201 Southwest Freeway |
| Coordinates | 29.72812, -95.44508 |
| Website | databank.com |
Power and grid
| Nearest high-voltage substation | Bellaire Substation, 345 kV, 700 m away (CenterPoint Energy) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 33 |
| Utility | San Bernard Electric Coop, INC (cooperative) Electric retail service territory (HIFLD, US government). |
| Balancing authority | ERCO |
| Nearest gas pipeline | Kinder Morgan Texas Pipeline Co, intrastate pipeline, 8.5 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 18 GW in 52 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 379 g CO₂ per kWh (Texas, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 48.3%, wind 21.7%, coal 11.6%, solar 10.7%, nuclear 7%. Clean power: 39.8% |
| Industrial power price | USD 0.072 per kWh (Texas, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 21 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 42.1 °C (2001 to 2025) |
| Cooling degree days | 1,811 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.65 kWh per m² per day |
| Wind at 50 m | 5.9 m/s average |
| Water stress today | High (40-80%) (Texas) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | High (40-80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Databank Houston Galleria (HOU5) to the power grid?
The nearest high-voltage substation in OpenStreetMap is Bellaire Substation (345 kV), about 700 m away. The local utility is San Bernard Electric Coop, INC, in the ERCO balancing area.
How clean is the power for Databank Houston Galleria (HOU5)?
The grid in Texas emits about 379 g CO₂ per kWh (2025). Largest sources: gas 48.3%, wind 21.7%, coal 11.6%.
Who operates Databank Houston Galleria (HOU5)?
DataBank.
Data centers near Houston
- Data Foundry Houston 1 3.5 km
- 3500 Garrott 5.9 km
- Rice Data Center 7.8 km · 5 MW
- InterConnX Realty 7.8 km
- Netrality Houston - 1301 Fannin 8.1 km
- Alpheus Houston (777 Walker Street) 8.4 km
- Quasar Data Center 8.8 km
- Data center in Jersey Village 16.0 km · 11 MW
More DataBank data centers
- Databank Orangeburg (LGA3) United States
- DataBank Salt Lake City (SLC2) United States
- DataBank Ashburn (IAD1) United States
- DataBank Dallas (DFW3) United States
- DataBank Las Vegas (LAS1) United States
- DataBank Dallas (DFW4) United States
- DataBank Minneapolis (MSP3) United States
- DataBank Seattle (SEA2) United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.