EdgeConneX Pittsburgh (EDCPIT01)
EdgeConneX Pittsburgh (EDCPIT01) is an operational data center operated by EdgeConneX in Pittsburgh, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | EdgeConneX |
| Networks | 5 networks, 1 internet exchanges PeeringDB. |
| Address | 282 Corliss St |
| Coordinates | 40.45222, -80.04152 |
| Website | edgeconnex.com |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 138 kV, 1.3 km away (Duquesne Light) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Unnamed substation, 345 kV, 1.5 km away |
| HV substations within 10 km | 15 |
| Utility | Duquesne Light Co (investor owned) Electric retail service territory (HIFLD, US government). |
| Balancing authority | PJM |
| Nearest gas pipeline | Equitrans Inc, interstate pipeline, 5.2 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 4.3 GW in 17 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 387 g CO₂ per kWh (Pennsylvania, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 58%, nuclear 30.3%, coal 7.1%, wind 1.4%, solar 1.4%. Clean power: 34.3% |
| Industrial power price | USD 0.105 per kWh (Pennsylvania, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 10.6 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 37.7 °C (2001 to 2025) |
| Cooling degree days | 470 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.72 kWh per m² per day |
| Wind at 50 m | 4.4 m/s average |
| Water stress today | Low - Medium (10-20%) (Pennsylvania) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is EdgeConneX Pittsburgh (EDCPIT01) to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (138 kV), about 1.3 km away. The local utility is Duquesne Light Co, in the PJM balancing area.
How clean is the power for EdgeConneX Pittsburgh (EDCPIT01)?
The grid in Pennsylvania emits about 387 g CO₂ per kWh (2025). Largest sources: gas 58%, nuclear 30.3%, coal 7.1%.
Who operates EdgeConneX Pittsburgh (EDCPIT01)?
EdgeConneX.
Data centers near Pittsburgh
- Expedient Pittsburgh - Green Tree 2.8 km · 5 MW
- Zayo Pittsburgh - 2500 Allegheny Center Mall 2.9 km
- Expedient Pittsburgh - Nova Place 3.0 km
- Crown Castle Pittsburgh (Allegheny Center Mall) 3.1 km
- Citynet Pittsburgh 3.3 km
- DQE Communications (Downtown Pittsburgh) 3.8 km
- H5 Data Centers Pittsburgh (PA02) 5.2 km
- Lumen Pittsburgh 6.7 km
More EdgeConneX data centers
- EdgeConneX PHX02 Data Center United States
- EdgeConneX data center in Oosteinde Netherlands
- EdgeConnex DUB04 Ireland
- EdgeConneX Germany
- EdgeConneX Chicago (EDCCHI02) United States
- EdgeConneX data center in Oosteinde Netherlands
- EdgeConneX data center in Oosteinde Netherlands
- EdgeConnex - DEN02 United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.