Equinix CU1/CU2/CU3/CU4 - Culpeper is an operational data center operated by Equinix in Culpeper, United States. Our footprint estimate of its power is about 25 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Equinix |
| Facility power | 25 MW (range 9.8 MW to 62 MW) Estimate from building footprint, low confidence. Footprint estimate: about 205,100 m² site outline x 0.12 kW per m² of land. |
| GPU capacity if all AI | about 11,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Networks | 10 networks, 1 internet exchanges PeeringDB. |
| Also known as | Equinix CU2 |
| Address | 18155 Technology Dr. |
| Coordinates | 38.45488, -77.97832 |
| Website | equinix.com |
Power and grid
| Nearest high-voltage substation | Mountain Run Substation, 115 kV, 1 km away (Virginia Electric and Power Company) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Remington Substation, 230 kV, 19.9 km away |
| HV substations within 10 km | 4 |
| Utility | Rappahannock Electric Coop (cooperative) Electric retail service territory (HIFLD, US government). |
| Balancing authority | PJM |
| Nearest gas pipeline | Transcontinental Gas PL, interstate pipeline, 10.5 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 4.4 GW in 10 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 357 g CO₂ per kWh (Virginia, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 56.7%, nuclear 26.4%, solar 9.5%, coal 3.4%, bioenergy 3.3%. Clean power: 39% |
| Industrial power price | USD 0.100 per kWh (Virginia, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 12.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 41.1 °C (2001 to 2025) |
| Cooling degree days | 742 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.12 kWh per m² per day |
| Wind at 50 m | 4.2 m/s average |
| Water stress today | Medium - High (20-40%) (Virginia) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Equinix CU1/CU2/CU3/CU4 - Culpeper use?
We estimate the facility power at about 25 MW. Estimate from building footprint, low confidence.
How close is Equinix CU1/CU2/CU3/CU4 - Culpeper to the power grid?
The nearest high-voltage substation in OpenStreetMap is Mountain Run Substation (115 kV), about 1 km away. The local utility is Rappahannock Electric Coop, in the PJM balancing area.
How clean is the power for Equinix CU1/CU2/CU3/CU4 - Culpeper?
The grid in Virginia emits about 357 g CO₂ per kWh (2025). Largest sources: gas 56.7%, nuclear 26.4%, solar 9.5%.
Who operates Equinix CU1/CU2/CU3/CU4 - Culpeper?
Equinix.
Data centers near Culpeper
- Data center in Warrenton 34.2 km · 18 MW
- OVH US East Vint Hill 41.9 km · 9.6 MW
- Google Bristow 48.4 km · 286 MW
- Digital Realty GNV (8217 Linton Hall) 48.8 km
- Digital Realty VA4 49.0 km · 12 MW
- Amazon Web Services data center in Gainesville 49.1 km · 15 MW
- Amazon IAD-55 49.2 km · 37 MW
- Google Mango Farm 49.3 km · 60 MW
More Equinix data centers
- Equinix DA1 - Dallas United States
- Equinix SP6 Brazil
- Equinix PH1 - Philadelphia United States
- Equinix PA13X France
- Equinix CH1/CH2/CH4 - Chicago United States
- Equinix CH3 - Elk Grove United States
- Equinix AM3 - Amsterdam, Science Park Netherlands
- Equinix LA1 - Los Angeles United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.