Equinix DB2 - Dublin, Kilcarbery
Equinix DB2 - Dublin, Kilcarbery is an operational data center operated by Equinix in Dublin, Ireland. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Equinix |
| Networks | 52 networks, 4 internet exchanges PeeringDB. |
| Address | Kilcarbery Business Park, Nangor Road |
| Coordinates | 53.31865, -6.43996 |
| Website | equinix.com/locations/ireland-colocation/dublin-data-centers/db2 |
Power and grid
| Nearest high-voltage substation | Kilcarbery Substation, 110 kV, 500 m away (EirGrid) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Castlebaggot 220kV Substation, 220 kV, 700 m away |
| HV substations within 10 km | 32 |
| Power plants within 50 km | 3.5 GW in 41 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 261 g CO₂ per kWh (Ireland, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 48.1%, wind 37.8%, solar 4.7%, bioenergy 3.3%, oil and other fossil 2.9%. Clean power: 47.8% |
| Industrial power price | EUR 0.206 per kWh (Ireland, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 10.1 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 24.3 °C (2001 to 2025) |
| Cooling degree days | 1 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.74 kWh per m² per day |
| Wind at 50 m | 8 m/s average |
| Water stress today | Low (<10%) (Ireland) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Low (<10%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Equinix DB2 - Dublin, Kilcarbery to the power grid?
The nearest high-voltage substation in OpenStreetMap is Kilcarbery Substation (110 kV), about 500 m away.
How clean is the power for Equinix DB2 - Dublin, Kilcarbery?
The grid in Ireland emits about 261 g CO₂ per kWh (2025). Largest sources: gas 48.1%, wind 37.8%, solar 4.7%.
Who operates Equinix DB2 - Dublin, Kilcarbery?
Equinix.
Data centers near Dublin
- Digital Realty Dublin DUB13-14 94 m · 4.1 MW
- Microsoft DSF 217 m · 9 MW
- Data center in Clondalkin 329 m · 18 MW
- Microsoft DUB06 415 m · 24 MW
- Microsoft DUB13 458 m · 12 MW
- Digital Realty DUB3 601 m · 5.8 MW
- Microsoft Grange Castle 643 m · 111 MW
- Data center in Clondalkin 741 m · 21 MW
More Equinix data centers
- Equinix DA1 - Dallas United States
- Equinix SP6 Brazil
- Equinix PH1 - Philadelphia United States
- Equinix PA13X France
- Equinix CH1/CH2/CH4 - Chicago United States
- Equinix CH3 - Elk Grove United States
- Equinix AM3 - Amsterdam, Science Park Netherlands
- Equinix LA1 - Los Angeles United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.