FSIT Dietikon CH-DIE001
FSIT Dietikon CH-DIE001 is an operational data center operated by FSIT in Dietikon, Switzerland. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | FSIT |
| Networks | 1 networks PeeringDB. |
| Address | Lerzenstrasse 27 |
| Coordinates | 47.41953, 8.39635 |
| Website | fsit.com |
Power and grid
| Nearest high-voltage substation | Unterwerk Dietikon, 110 kV, 1.2 km away (Axpo/EKZ) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Unterwerk Spreitenbach, 220 kV, 1.5 km away |
| HV substations within 10 km | 16 |
| Power plants within 50 km | 6.3 GW in 59 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 39 g CO₂ per kWh (Switzerland, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 52.3%, nuclear 29.9%, solar 12.1%, oil and other fossil 1.9%, bioenergy 1.6%. Clean power: 97.7% |
Climate and water
| Average temperature | 9.1 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 33.5 °C (2001 to 2025) |
| Cooling degree days | 117 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.4 kWh per m² per day |
| Wind at 50 m | 4.3 m/s average |
| Water stress today | Low (<10%) (Switzerland) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Low (<10%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is FSIT Dietikon CH-DIE001 to the power grid?
The nearest high-voltage substation in OpenStreetMap is Unterwerk Dietikon (110 kV), about 1.2 km away.
How clean is the power for FSIT Dietikon CH-DIE001?
The grid in Switzerland emits about 39 g CO₂ per kWh (2025). Largest sources: hydro 52.3%, nuclear 29.9%, solar 12.1%.
Who operates FSIT Dietikon CH-DIE001?
FSIT.
Data centers near Dietikon
- Green Datacenter ZRH3 (fka: Green Schlieren) 3.6 km · 0.8 MW
- Equinix ZH5 - Zurich, South 5.2 km · 7.2 MW
- Templus DC Zurich ZRH01 6.5 km
- Data center in Zürich 8.3 km · 5.9 MW
- Green Datacenter ZRH2 (fka: Green Dielsdorf) 8.5 km · 5.8 MW
- colozueri.ch Zurich 8.5 km
- Rechenzentrum Albis 8.8 km · 4.6 MW
- Equinix ZH2 - Zurich 10.0 km