Global Switch London East is an operational data center operated by Global Switch in London, United Kingdom. Our footprint estimate of its power is about 38 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Global Switch |
| Facility power | 38 MW (range 19 MW to 61 MW) Estimate from building footprint, low confidence. Footprint estimate: about 10,523 m² building outline x 3 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 16,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Networks | 31 networks, 1 internet exchanges PeeringDB. |
| Also known as | EXA Datacenter London (GS2 London East) · Global Switch London North |
| Address | 3 Nutmeg Lane |
| Coordinates | 51.51098, -0.00349 |
| Website | globalswitch.com |
Power and grid
| Nearest high-voltage substation | Telehouse Substation, 132 kV, 100 m away (Telehouse) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | West Ham Substation, 400 kV, 1 km away |
| HV substations within 10 km | 52 |
| Power plants within 50 km | 3.1 GW in 97 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 218 g CO₂ per kWh (United Kingdom, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 31.3%, wind 29.4%, bioenergy 13.9%, nuclear 12.4%, solar 6.6%. Clean power: 64.2% |
Climate and water
| Average temperature | 10.4 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 34 °C (2001 to 2025) |
| Cooling degree days | 46 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.97 kWh per m² per day |
| Wind at 50 m | 7.2 m/s average |
| Water stress today | Low - Medium (10-20%) (England) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Global Switch London East use?
We estimate the facility power at about 38 MW. Estimate from building footprint, low confidence.
How close is Global Switch London East to the power grid?
The nearest high-voltage substation in OpenStreetMap is Telehouse Substation (132 kV), about 100 m away.
How clean is the power for Global Switch London East?
The grid in United Kingdom emits about 218 g CO₂ per kWh (2025). Largest sources: gas 31.3%, wind 29.4%, bioenergy 13.9%.
Who operates Global Switch London East?
Global Switch.
Data centers near London
- Telehouse North 159 m · 31 MW
- Telehouse - London (Docklands South) 439 m · 37 MW
- Global Switch London North 496 m
- IP House Data Centre 637 m · 3.6 MW
- Cable & Wireless Data Centre 1.1 km · 1.3 MW
- Netwise London East (NLE) 1.1 km
- EXA Datacenter London (Citi) 1.3 km
- Digital Realty London LHR20 1.3 km · 1.5 MW
More Global Switch data centers
- Global Switch Singapore Singapore
- Global Switch Amsterdam Netherlands
- Global Switch Paris France
- Global Switch Frankfurt Germany
- Global Switch Hong Kong Hong Kong SAR China
- Global Switch London North United Kingdom
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.