Intellicentre 4 Bunker
Intellicentre 4 Bunker is an operational data center operated by Macquarie Telecom in Campbell, Australia. Our footprint estimate of its power is about 3.1 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Macquarie Telecom |
| Facility power | 3.1 MW (range 1.6 MW to 5 MW) Estimate from building footprint, low confidence. Footprint estimate: about 2,608 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 1,300 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Also known as | Intellicentre 5 Bunker |
| Address | Pearce Avenue 6 |
| Coordinates | -35.30105, 149.20211 |
| Website | macquariedatacentres.com/data-centres/canberra-ic4-data-centre |
Power and grid
| Nearest high-voltage substation | East Lake Zone Substation, 132 kV, 3.8 km away (Evoenergy) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Unnamed substation, 500 kV, 7.4 km away |
| HV substations within 10 km | 8 |
| Power plants within 50 km | 194 MW in 8 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 518 g CO₂ per kWh (Australia, 2025) Average of all power made in the area. Ember. |
| Grid power mix | coal 42.9%, solar 20.4%, gas 15.5%, wind 13.8%, hydro 4.4%. Clean power: 39.8% |
Climate and water
| Average temperature | 11 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 37.3 °C (2001 to 2025) |
| Cooling degree days | 133 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.79 kWh per m² per day |
| Wind at 50 m | 3.5 m/s average |
| Water stress today | Medium - High (20-40%) (Australian Capital Territory) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Intellicentre 4 Bunker use?
We estimate the facility power at about 3.1 MW. Estimate from building footprint, low confidence.
How close is Intellicentre 4 Bunker to the power grid?
The nearest high-voltage substation in OpenStreetMap is East Lake Zone Substation (132 kV), about 3.8 km away.
How clean is the power for Intellicentre 4 Bunker?
The grid in Australia emits about 518 g CO₂ per kWh (2025). Largest sources: coal 42.9%, solar 20.4%, gas 15.5%.
Who operates Intellicentre 4 Bunker?
Macquarie Telecom.
Data centers near Campbell
- Verizon data center in Narrabundah 3.0 km · 2.4 MW
- Fyshwick 2 4.5 km · 13 MW
- CDC Canberra FY1 4.5 km
- Department of Defence data center in Queanbeyan 5.6 km · 6.7 MW
- TransACT Telehouse 8.3 km · 0.9 MW
- Iron Mountain 10.1 km · 23 MW
- CSIRO Virga 10.3 km · 0.6 MW
- CDC Hume Datacentre 3 10.3 km · 7.8 MW
Sources
Correct this page or get the data