KOMO Plaza Seattle (Formerly Fisher Plaza)
KOMO Plaza Seattle (Formerly Fisher Plaza) is an operational data center operated by GI Property Management in Seattle, United States. Our footprint estimate of its power is about 38 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | GI Property Management |
| Facility power | 38 MW (range 19 MW to 60 MW) Estimate from building footprint, low confidence. Footprint estimate: about 5,236 m² building outline x 6 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 16,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Networks | 23 networks, 2 internet exchanges PeeringDB. |
| Also known as | Evocative SEA1 · TierPoint Seattle · KOMO Plaza East · KOMO Plaza West |
| Address | 140 4th Ave N |
| Opened | 2000 |
| Coordinates | 47.61924, -122.34828 |
| Website | komoplaza.com |
Power and grid
| Nearest high-voltage substation | Broad Street Substation, 115 kV, 300 m away (Seattle City Light) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | East Pine Substation, 230 kV, 3.4 km away |
| HV substations within 10 km | 8 |
| Utility | City Of Seattle (municipal) Electric retail service territory (HIFLD, US government). |
| Balancing authority | SCL |
| Nearest gas pipeline | Northwest Pipeline, interstate pipeline, 20.6 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 126 MW in 7 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 135 g CO₂ per kWh (Washington, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 62.8%, gas 15.7%, wind 8.3%, nuclear 7.5%, coal 3%. Clean power: 80.9% |
| Industrial power price | USD 0.074 per kWh (Washington, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 10.5 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 38 °C (2001 to 2025) |
| Cooling degree days | 79 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.42 kWh per m² per day |
| Wind at 50 m | 3.5 m/s average |
| Water stress today | Low - Medium (10-20%) (Washington) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does KOMO Plaza Seattle (Formerly Fisher Plaza) use?
We estimate the facility power at about 38 MW. Estimate from building footprint, low confidence.
How close is KOMO Plaza Seattle (Formerly Fisher Plaza) to the power grid?
The nearest high-voltage substation in OpenStreetMap is Broad Street Substation (115 kV), about 300 m away. The local utility is City Of Seattle, in the SCL balancing area.
How clean is the power for KOMO Plaza Seattle (Formerly Fisher Plaza)?
The grid in Washington emits about 135 g CO₂ per kWh (2025). Largest sources: hydro 62.8%, gas 15.7%, wind 8.3%.
Who operates KOMO Plaza Seattle (Formerly Fisher Plaza)?
GI Property Management.
Data centers near Seattle
- Digital Fortress (SEA) 651 m · 13 MW
- Equinix SE3 Data Center 834 m · 11 MW
- Digital Realty Seattle SEA10 890 m · 13 MW
- Level(3) Seattle (Denny Way) 891 m · 30 MW
- SBTC 1.0 km
- Comcast data center in Greenwood 8.6 km · 0.7 MW
- EdgeConneX Seattle (EDCSEA01) 14.2 km
- DataBank Seattle (SEA2) 14.5 km · 9.3 MW
More GI Property Management data centers
- 43915 Devin Shafron United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.