Meta is an operational data center operated by Meta in Altoona, United States. Our footprint estimate of its power is about 69 MW. Likely chips: NVIDIA GPUs (some Meta MTIA) (guess).

Key facts

StatusOperational
OperatorMeta
Facility power69 MW (range 34 MW to 110 MW)
Estimate from building footprint, low confidence. Footprint estimate: about 57,385 m² building outline x 1 floor(s) x 1.2 kW/m².
AI chipsNVIDIA GPUs (some Meta MTIA)
Guess from the operator, not confirmed. Meta trains on NVIDIA GPUs and adds in-house MTIA chips for inference.
GPU capacity if all AIabout 29,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Coordinates41.67578, -93.50983

Power and grid

UtilityMidamerican Energy Co (investor owned)
Electric retail service territory (HIFLD, US government).
Balancing authorityMISO
Nearest gas pipelineNorthern Natural Gas Co, interstate pipeline, 2.4 km away
US Energy Information Administration pipeline map. Straight-line distance.
Grid carbon intensity313 g CO₂ per kWh (Iowa, 2025)
Average of all power made in the area. Ember.
Grid power mixwind 58.5%, coal 25.6%, gas 11.6%, solar 2.5%, hydro 1.4%. Clean power: 62.8%
Industrial power priceUSD 0.093 per kWh (Iowa, August 2026)
Average price paid by industrial users in the state. EIA Electric Power Monthly.

Climate and water

Average temperature10.2 °C
NASA POWER, average of 2001 to 2025.
Highest temperature42.6 °C (2001 to 2025)
Cooling degree days586 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy4.09 kWh per m² per day
Wind at 50 m6.9 m/s average
Water stress todayLow - Medium (10-20%) (Iowa)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050Low - Medium (10-20%)
Business-as-usual scenario.

Satellite view

Questions

How much power does Meta use?

We estimate the facility power at about 69 MW. Estimate from building footprint, low confidence.

What chips does Meta use?

No chips are reported. Based on the operator, the likely chips are NVIDIA GPUs (some Meta MTIA).

How clean is the power for Meta?

The grid in Iowa emits about 313 g CO₂ per kWh (2025). Largest sources: wind 58.5%, coal 25.6%, gas 11.6%.

Who operates Meta?

Meta.

Data centers near Altoona

More Meta data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.