Meta Sarpy is an operational AI data center operated by Meta in Springfield, United States. Its power is about 105 MW. Epoch AI estimates about 92,000 H100-equivalent AI chips (B300).

Key facts

StatusOperational
OperatorMeta
UsersMeta
Facility power105 MW
Reported (Epoch AI or owner data)
IT power80 MW
AI compute92,000 H100-equivalents
AI chipsB300
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 44,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 3.0 billion
Epoch AI estimate, 2025 USD.
Address14436-14998 Fairview Rd, Springfield, NE 68059, USA
Coordinates41.08184, -96.13109 (city level)

Power and grid

UtilityOmaha Public Power District (political subdivision)
Electric retail service territory (HIFLD, US government).
Balancing authoritySWPP
Nearest gas pipelineNorthern Natural Gas Co, interstate pipeline, 1.7 km away
US Energy Information Administration pipeline map. Straight-line distance.
Grid carbon intensity460 g CO₂ per kWh (Nebraska, 2025)
Average of all power made in the area. Ember.
Grid power mixcoal 46%, wind 29.4%, nuclear 17.4%, gas 3.2%, hydro 2.9%. Clean power: 50.7%
Industrial power priceUSD 0.084 per kWh (Nebraska, August 2026)
Average price paid by industrial users in the state. EIA Electric Power Monthly.

Climate and water

Average temperature11 °C
NASA POWER, average of 2001 to 2025.
Highest temperature43.1 °C (2001 to 2025)
Cooling degree days707 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy4.16 kWh per m² per day
Wind at 50 m7.1 m/s average
Water stress todayExtremely High (>80%) (Nebraska)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050Extremely High (>80%)
Business-as-usual scenario.

Build timeline

DatePowerH100eWhat the satellite images and filings show
2024-08-0100Building 1 grading underway.
2026-05-0400Building 1 shell, electrical and cooling equipment looks complete, with minimal construction work, so we expect it to be operational within 3 months.
2026-08-02105 MW92,000Building 1 is operational (estimate).

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2026-08-02B30036,300Estimate

Satellite view

Questions

How much power does Meta Sarpy use?

Public data puts the facility power at about 105 MW. Reported (Epoch AI or owner data).

What chips does Meta Sarpy use?

Reported chips: B300.

How clean is the power for Meta Sarpy?

The grid in Nebraska emits about 460 g CO₂ per kWh (2025). Largest sources: coal 46%, wind 29.4%, nuclear 17.4%.

Who operates Meta Sarpy?

Meta. Reported users: Meta.

Data centers near Springfield

More Meta data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.