QTS Ashburn Lockridge
QTS Ashburn Lockridge is an operational data center operated by Quality Technology Services in Sterling, United States. Our footprint estimate of its power is about 13 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Quality Technology Services |
| Facility power | 13 MW (range 5.1 MW to 32 MW) Estimate from building footprint, low confidence. Footprint estimate: about 105,714 m² site outline x 0.12 kW per m² of land. |
| GPU capacity if all AI | about 5,600 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Also known as | QTS Ashburn 2 DC1 · QTS Ashburn 2 DC2 |
| Coordinates | 38.99593, -77.45624 |
| Website | q.com/data-centers/ashburn-2 |
Power and grid
| Nearest high-voltage substation | Lockridge Substation, 230 kV, 100 m away (Virginia Electric & Power Company) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 54 |
| Utility | Virginia Electric & Power Co (investor owned) Electric retail service territory (HIFLD, US government). |
| Balancing authority | PJM |
| Nearest gas pipeline | Columbia Gas Trans Co, interstate pipeline, 800 m away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 1.6 GW in 43 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 357 g CO₂ per kWh (Virginia, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 56.7%, nuclear 26.4%, solar 9.5%, coal 3.4%, bioenergy 3.3%. Clean power: 39% |
| Industrial power price | USD 0.100 per kWh (Virginia, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 12.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 40.7 °C (2001 to 2025) |
| Cooling degree days | 729 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.98 kWh per m² per day |
| Wind at 50 m | 5.3 m/s average |
| Water stress today | Medium - High (20-40%) (Virginia) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does QTS Ashburn Lockridge use?
We estimate the facility power at about 13 MW. Estimate from building footprint, low confidence.
How close is QTS Ashburn Lockridge to the power grid?
The nearest high-voltage substation in OpenStreetMap is Lockridge Substation (230 kV), about 100 m away. The local utility is Virginia Electric & Power Co, in the PJM balancing area.
How clean is the power for QTS Ashburn Lockridge?
The grid in Virginia emits about 357 g CO₂ per kWh (2025). Largest sources: gas 56.7%, nuclear 26.4%, solar 9.5%.
Who operates QTS Ashburn Lockridge?
Quality Technology Services.
Data centers near Sterling
- Sentinel Ashburn - Building 1 302 m · 16 MW
- Amazon IAD-285 530 m · 12 MW
- Amazon IAD-76 550 m · 22 MW
- QTS Ashburn 1 DC1 664 m · 72 MW
- QTS Ashburn Moran 721 m · 5 MW
- Digital Realty IAD43 724 m · 65 MW
- QTS Ashburn (ASH1) 811 m · 4.4 MW
- Amazon IAD-15 813 m · 21 MW
More Quality Technology Services data centers
- QTS Richmond 1 United States
- QTS Piscataway Data Center United States
- QTS Richmond 2 Data Center United States
- QTS Richmond 3 Data Center United States
- QTS Ashburn 1 DC1 United States
- DC5 United States
- QTS United States
- QTS Ashburn-Shellhorn United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.