QTS Ashburn 1 DC1
QTS Ashburn 1 DC1 is an operational data center operated by Quality Technology Services in Sterling, United States. Its power is about 72 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Quality Technology Services |
| Facility power | 72 MW Derived from a tagged IT power value. IT power tag in OpenStreetMap |
| IT power | 55 MW |
| GPU capacity if all AI | about 31,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Also known as | QTS Ashburn 1 DC2 |
| Address | Broderick Drive 22271, 20166, Sterling |
| Coordinates | 38.99953, -77.45011 |
| Website | q.com/data-centers/ashburn-1 |
Power and grid
| Nearest high-voltage substation | Lockridge Substation, 230 kV, 600 m away (Virginia Electric & Power Company) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 50 |
| Utility | Virginia Electric & Power Co (investor owned) Electric retail service territory (HIFLD, US government). |
| Balancing authority | PJM |
| Nearest gas pipeline | Columbia Gas Trans Co, interstate pipeline, 1.2 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 1.6 GW in 43 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 357 g CO₂ per kWh (Virginia, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 56.7%, nuclear 26.4%, solar 9.5%, coal 3.4%, bioenergy 3.3%. Clean power: 39% |
| Industrial power price | USD 0.100 per kWh (Virginia, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 12.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 40.7 °C (2001 to 2025) |
| Cooling degree days | 729 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.98 kWh per m² per day |
| Wind at 50 m | 5.3 m/s average |
| Water stress today | Medium - High (20-40%) (Virginia) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does QTS Ashburn 1 DC1 use?
Public data puts the facility power at about 72 MW. Derived from a tagged IT power value.
How close is QTS Ashburn 1 DC1 to the power grid?
The nearest high-voltage substation in OpenStreetMap is Lockridge Substation (230 kV), about 600 m away. The local utility is Virginia Electric & Power Co, in the PJM balancing area.
How clean is the power for QTS Ashburn 1 DC1?
The grid in Virginia emits about 357 g CO₂ per kWh (2025). Largest sources: gas 56.7%, nuclear 26.4%, solar 9.5%.
Who operates QTS Ashburn 1 DC1?
Quality Technology Services.
Data centers near Sterling
- QTS Ashburn (ASH1) 147 m · 4.4 MW
- Digital Realty IAD43 340 m · 65 MW
- PowerHouse Pacific Building 2 460 m · 15 MW
- PowerHouse Pacific Building 3 536 m · 14 MW
- VeriSign Incorporated 574 m · 23 MW
- EdgeCore AS02 610 m · 55 MW
- QTS Ashburn Moran 613 m · 5 MW
- Amazon IAD-76 639 m · 22 MW
More Quality Technology Services data centers
- QTS Richmond 1 United States
- QTS Piscataway Data Center United States
- QTS Richmond 2 Data Center United States
- QTS Richmond 3 Data Center United States
- DC5 United States
- QTS United States
- QTS Ashburn-Shellhorn United States
- RIC3 DC5 United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.