RIC3 DC5

RIC3 DC5 is a data center under construction operated by Quality Technology Services in Sandston, United States. Our footprint estimate of its power is about 54 MW.

Power demand is growing at this site

Key facts

StatusUnder construction
OperatorQuality Technology Services
Facility power54 MW (range 27 MW to 86 MW)
Estimate from building footprint, low confidence. Footprint estimate: about 44,737 m² building outline x 1 floor(s) x 1.2 kW/m².
GPU capacity if all AIabout 23,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Also known asRIC3 DC4
AddressPortugee Road 3543, 23150, Sandston
Coordinates37.47702, -77.24969

Power and grid

UtilityVirginia Electric & Power Co (investor owned)
Electric retail service territory (HIFLD, US government).
Balancing authorityPJM
Nearest gas pipelineVirginia Natural Gas Co, intrastate pipeline, 2.8 km away
US Energy Information Administration pipeline map. Straight-line distance.
Grid carbon intensity357 g CO₂ per kWh (Virginia, 2025)
Average of all power made in the area. Ember.
Grid power mixgas 56.7%, nuclear 26.4%, solar 9.5%, coal 3.4%, bioenergy 3.3%. Clean power: 39%
Industrial power priceUSD 0.100 per kWh (Virginia, August 2026)
Average price paid by industrial users in the state. EIA Electric Power Monthly.

Climate and water

Average temperature14.8 °C
NASA POWER, average of 2001 to 2025.
Highest temperature40.7 °C (2001 to 2025)
Cooling degree days940 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy4.31 kWh per m² per day
Wind at 50 m4.6 m/s average
Water stress todayMedium - High (20-40%) (Virginia)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050Medium - High (20-40%)
Business-as-usual scenario.

Satellite view

Questions

How much power does RIC3 DC5 use?

We estimate the facility power at about 54 MW. Estimate from building footprint, low confidence.

How clean is the power for RIC3 DC5?

The grid in Virginia emits about 357 g CO₂ per kWh (2025). Largest sources: gas 56.7%, nuclear 26.4%, solar 9.5%.

Who operates RIC3 DC5?

Quality Technology Services.

Data centers near Sandston

More Quality Technology Services data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.