Southgate Melbourne
Southgate Melbourne is an operational AI data center operated by Firmus in Melbourne, Australia. Its power is about 57 MW. Epoch AI estimates about 46,000 H100-equivalent AI chips (B300).
Key facts
| Status | Operational |
|---|---|
| Operator | Firmus |
| Facility power | 57 MW Reported (Epoch AI or owner data) |
| IT power | 41 MW |
| AI compute | 46,000 H100-equivalents |
| AI chips | B300 Reported (Epoch AI or owner data) |
| GPU capacity if all AI | about 23,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Capital cost | USD 1.6 billion Epoch AI estimate, 2025 USD. |
| Coordinates | -37.82536, 144.96402 (city level) |
Power and grid
| Grid carbon intensity | 518 g CO₂ per kWh (Australia, 2025) Average of all power made in the area. Ember. |
|---|---|
| Grid power mix | coal 42.9%, solar 20.4%, gas 15.5%, wind 13.8%, hydro 4.4%. Clean power: 39.8% |
Climate and water
| Average temperature | 14.7 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 41.9 °C (2001 to 2025) |
| Cooling degree days | 279 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.43 kWh per m² per day |
| Wind at 50 m | 6.2 m/s average |
| Water stress today | High (40-80%) (Victoria) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | High (40-80%) Business-as-usual scenario. |
Build timeline
| Date | Power | H100e | What the satellite images and filings show |
|---|---|---|---|
| 2022-12-26 | 0 | 0 | Building 1 site is cleared/vacant land; no construction visible yet (based on Google Earth historical imagery). |
| 2025-10-28 | 0 | 0 | Satellite imagery shows 30 fully installed air-cooled chillers (20 fans each) on the roof, with room for many more. In the same month, Firmus [reported](https://firmus.co/newsroom/southgate-expansion) that Project Southgate's "first stages are under construction in Tasmania and Melbourne". So we don't think the Southgate part of the building is operational yet. |
| 2026-05-11 | 0 | 0 | Building 1's cooling capacity increased to 53 air-cooled chillers (20 fans each), up from 30 in Oct 2025. This is more than enough for the announced 18,400 GB300 GPUs, but construction does not quite look complete, so we expect another 3 months until it's operational. |
| 2026-08-09 | 57 MW | 46,000 | Building 1 is operational (estimate). No additional chip deployment beyond the 18,400 GB300 GPUs has been publicly confirmed, so we continue to report the disclosed capacity allocated to Project Southgate, rather than speculate on further buildout. |
Source: Epoch AI Frontier Data Centers.
Chip deployments
| Date | Chip | Units | Basis |
|---|---|---|---|
| 2026-08-09 | B300 | 18,400 | Reported |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Southgate Melbourne use?
Public data puts the facility power at about 57 MW. Reported (Epoch AI or owner data).
What chips does Southgate Melbourne use?
Reported chips: B300.
How clean is the power for Southgate Melbourne?
The grid in Australia emits about 518 g CO₂ per kWh (2025). Largest sources: coal 42.9%, solar 20.4%, gas 15.5%.
Who operates Southgate Melbourne?
Firmus.
Data centers near Melbourne
- Datacom Data Centre 250 m · 2.1 MW
- Powertel Data Centre 757 m · 2.1 MW
- PIPE Networks Melbourne 940 m · 1.8 MW
- 5GN Melbourne Data Centre (MDC) 1.1 km
- Equinix ME5 - Melbourne (formerly Metronode Melbourne 1) 2.1 km · 2.3 MW
- Interactive Melbourne 2.6 km · 3.5 MW
- NEXTDC M1 2.9 km · 10 MW
- Soul DataCentre 3.2 km · 1.1 MW
More Firmus data centers
- Firmus data center in Devonport Australia
- Firmus data center in Newnham Australia
- Firmus LST01 Australia
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.