STACK NVA02x is an operational data center operated by STACK Infrastructure in Manassas, United States. Our footprint estimate of its power is about 47 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | STACK Infrastructure |
| Facility power | 47 MW (range 23 MW to 75 MW) Estimate from building footprint, low confidence. Footprint estimate: about 39,051 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 20,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | Hornbaker Road 9522, 20109, Manassas |
| Coordinates | 38.74815, -77.53780 |
Power and grid
| Utility | Northern Virginia Elec Coop (cooperative) Electric retail service territory (HIFLD, US government). |
|---|---|
| Balancing authority | PJM |
| Nearest gas pipeline | Dominion Transmission Co, interstate pipeline, 1.1 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Grid carbon intensity | 357 g CO₂ per kWh (Virginia, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 56.7%, nuclear 26.4%, solar 9.5%, coal 3.4%, bioenergy 3.3%. Clean power: 39% |
| Industrial power price | USD 0.100 per kWh (Virginia, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 13.4 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 41.2 °C (2001 to 2025) |
| Cooling degree days | 808 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.12 kWh per m² per day |
| Wind at 50 m | 4.5 m/s average |
| Water stress today | Medium - High (20-40%) (Virginia) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does STACK NVA02x use?
We estimate the facility power at about 47 MW. Estimate from building footprint, low confidence.
How clean is the power for STACK NVA02x?
The grid in Virginia emits about 357 g CO₂ per kWh (2025). Largest sources: gas 56.7%, nuclear 26.4%, solar 9.5%.
Who operates STACK NVA02x?
STACK Infrastructure.
Data centers near Manassas
- STACK Infrastructure NVA02 214 m · 118 MW
- STACK NVA02E 300 m · 51 MW
- EvoSwitch WDC1 530 m · 19 MW
- STACK NVA02A 685 m · 21 MW
- Amazon IAD-132 782 m · 26 MW
- Data center in Linton Hall 1.5 km · 17 MW
- Amazon IAD-105 1.6 km · 62 MW
- Data center in Linton Hall 1.7 km · 5.3 MW
More STACK Infrastructure data centers
- STACK Infrastructure NVA02 United States
- STACK NVA05B United States
- STACK NVA06 United States
- STACK NVA02E United States
- STACK NVA05A United States
- Stack Infrastructure Portland PORO2 United States
- STACK NVA01A United States
- STACK NVA02A United States
Sources
Correct this page or get the data