STACK NVA06
STACK NVA06 is an operational data center operated by STACK Infrastructure in Leesburg, United States. Its power is about 62 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | STACK Infrastructure |
| Facility power | 62 MW Derived from a tagged IT power value. IT power tag in OpenStreetMap |
| IT power | 48 MW |
| GPU capacity if all AI | about 27,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | Compass Creek Parkway SE 19275 |
| Coordinates | 39.08219, -77.56512 |
| Website | stackinfra.com/locations/americas/northern-virginia/nva06 |
Power and grid
| Utility | Northern Virginia Elec Coop (cooperative) Electric retail service territory (HIFLD, US government). |
|---|---|
| Balancing authority | PJM |
| Nearest gas pipeline | Dominion Transmission Co, interstate pipeline, 900 m away US Energy Information Administration pipeline map. Straight-line distance. |
| Grid carbon intensity | 357 g CO₂ per kWh (Virginia, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 56.7%, nuclear 26.4%, solar 9.5%, coal 3.4%, bioenergy 3.3%. Clean power: 39% |
| Industrial power price | USD 0.100 per kWh (Virginia, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 12.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 40.7 °C (2001 to 2025) |
| Cooling degree days | 729 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.98 kWh per m² per day |
| Wind at 50 m | 5.3 m/s average |
| Water stress today | Medium - High (20-40%) (Virginia) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does STACK NVA06 use?
Public data puts the facility power at about 62 MW. Derived from a tagged IT power value.
How clean is the power for STACK NVA06?
The grid in Virginia emits about 357 g CO₂ per kWh (2025). Largest sources: gas 56.7%, nuclear 26.4%, solar 9.5%.
Who operates STACK NVA06?
STACK Infrastructure.
Data centers near Leesburg
- Microsoft Leesburg Building 1 828 m · 31 MW
- Microsoft Leesburg Building 4 1.5 km · 26 MW
- Microsoft Leesburg Building 5 1.9 km · 15 MW
- Amazon IAD-668 3.3 km · 29 MW
- Stonewall Creek Business Park 4.1 km · 15 MW
- Google Leesburg Building 3 4.3 km · 33 MW
- 42254 THUNDERBALL DR 4.8 km · 34 MW
- True North Data Centers 4.9 km · 81 MW
More STACK Infrastructure data centers
- STACK Infrastructure NVA02 United States
- STACK NVA05B United States
- STACK NVA02E United States
- STACK NVA02x United States
- STACK NVA05A United States
- Stack Infrastructure Portland PORO2 United States
- STACK NVA01A United States
- STACK NVA02A United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.