Stream Data Centers - Houston I
Stream Data Centers - Houston I is an operational data center operated by Stream Data Centers in The Woodlands, United States. Our footprint estimate of its power is about 22 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Stream Data Centers |
| Facility power | 22 MW (range 11 MW to 35 MW) Estimate from building footprint, low confidence. Footprint estimate: about 18,211 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 9,400 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Networks | 5 networks, 1 internet exchanges PeeringDB. |
| Also known as | Stream Data Centers Houston |
| Address | 4001 Technology Forest Blvd |
| Coordinates | 30.17780, -95.48649 |
| Website | streamdatacenters.com/datacenters/houston-the-woodlands |
Power and grid
| Nearest high-voltage substation | Gosling Substation, 138 kV, 800 m away (Entergy) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Rothwood Substation, 345 kV, 9.7 km away |
| HV substations within 10 km | 9 |
| Utility | Mid-South Electric Coop Assn (cooperative) Electric retail service territory (HIFLD, US government). |
| Balancing authority | ERCO |
| Nearest gas pipeline | Gulf South Pipeline Co, interstate pipeline, 3.8 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 4.4 GW in 12 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 379 g CO₂ per kWh (Texas, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 48.3%, wind 21.7%, coal 11.6%, solar 10.7%, nuclear 7%. Clean power: 39.8% |
| Industrial power price | USD 0.072 per kWh (Texas, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 20.5 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 42.7 °C (2001 to 2025) |
| Cooling degree days | 1,754 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.65 kWh per m² per day |
| Wind at 50 m | 5.3 m/s average |
| Water stress today | High (40-80%) (Texas) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | High (40-80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Stream Data Centers - Houston I use?
We estimate the facility power at about 22 MW. Estimate from building footprint, low confidence.
How close is Stream Data Centers - Houston I to the power grid?
The nearest high-voltage substation in OpenStreetMap is Gosling Substation (138 kV), about 800 m away. The local utility is Mid-South Electric Coop Assn, in the ERCO balancing area.
How clean is the power for Stream Data Centers - Houston I?
The grid in Texas emits about 379 g CO₂ per kWh (2025). Largest sources: gas 48.3%, wind 21.7%, coal 11.6%.
Who operates Stream Data Centers - Houston I?
Stream Data Centers.
Data centers near The Woodlands
- ExxonMobil Discovery 6 9.2 km · 5.7 MW
- TRG Datacenters Houston (HOU1) (HOU2) 12.7 km
- DXC Technology data center in Cypress 21.6 km · 33 MW
- Data Foundry Houston 2 26.6 km · 10 MW
- Cogent Houston 26.8 km
- Digital Realty HOU (12001 North Freeway) 26.9 km
- Houston Bunker 28.3 km
- Equinix HO1 - Houston 29.4 km
More Stream Data Centers data centers
- Stream Phoenix United States
- Stream Data Centers - DFW VII United States
- Stream Data Centers - Chicago II United States
- Stream Data Centers - San Antonio II United States
- Stream Data Centers United States
- Stream Data Centers - Chicago I United States
- Stream Data Centers - MN I United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.