CentriLogic Traders (TRA)
CentriLogic Traders (TRA) is an operational data center operated by CentriLogic in Mississauga, Canada. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | CentriLogic |
| Networks | 1 networks PeeringDB. |
| Address | 215 Traders Boulevard East, Unit 11 |
| Coordinates | 43.62832, -79.66994 |
| Website | centrilogic.com/mississauga-ontario-north-data-center |
Power and grid
| Nearest high-voltage substation | Tomken TS, 230 kV, 3.6 km away (Hydro One) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 8 |
| Power plants within 50 km | 2.6 GW in 6 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 192 g CO₂ per kWh (Canada, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 52.8%, gas 19.7%, nuclear 12.8%, wind 8%, coal 2.7%. Clean power: 76.5% |
Climate and water
| Average temperature | 9.1 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 32.2 °C (2001 to 2025) |
| Cooling degree days | 288 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.65 kWh per m² per day |
| Wind at 50 m | 7 m/s average |
| Water stress today | Low - Medium (10-20%) (Ontario) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is CentriLogic Traders (TRA) to the power grid?
The nearest high-voltage substation in OpenStreetMap is Tomken TS (230 kV), about 3.6 km away.
How clean is the power for CentriLogic Traders (TRA)?
The grid in Canada emits about 192 g CO₂ per kWh (2025). Largest sources: hydro 52.8%, gas 19.7%, nuclear 12.8%.
Who operates CentriLogic Traders (TRA)?
CentriLogic.
Data centers near Mississauga
- CentriLogic Mississauga (MIS) 4.4 km
- Cogent Mississauga 2 4.6 km
- Hut 8 GTA1 5.0 km
- 11:11 Systems 6.0 km · 9.1 MW
- Maxxam Analytics International Inc. 6.3 km · 19 MW
- CentriLogic Tranmere (TME) 6.8 km
- CGI 6.8 km · 3.5 MW
- 11:11 Systems 7.3 km · 6.7 MW
More CentriLogic data centers
- CentriLogic Arlington (ARL) United Kingdom
- CentriLogic Mississauga (MIS) Canada
- CentriLogic Rochester (ROC) United States
- CentriLogic Tranmere (TME) Canada
- CentriLogic York (YOR) Canada
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.