CoreSite - Los Angeles (LA2)
CoreSite - Los Angeles (LA2) is an operational data center operated by CoreSite in Los Angeles, United States. Our footprint estimate of its power is about 32 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | CoreSite |
| Facility power | 32 MW (range 16 MW to 52 MW) Estimate from building footprint, low confidence. Footprint estimate: about 13,502 m² building outline x 2 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 14,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Networks | 205 networks, 3 internet exchanges PeeringDB. |
| Also known as | CoreSite - Los Angeles (LA3) · USPO Terminal Annex · CoreSite - LA2 |
| Address | 900 N. Alameda |
| Opened | 1938 |
| Coordinates | 34.05810, -118.23536 |
| Website | coresite.com |
Power and grid
| Nearest high-voltage substation | Receiving Station A, 230 kV, 1.3 km away (Los Angeles Department of Water and Power) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 4 |
| Utility | Los Angeles Department Of Water & Power (municipal) Electric retail service territory (HIFLD, US government). |
| Balancing authority | LDWP |
| Nearest gas pipeline | Southern California Gas Co, intrastate pipeline, 5.2 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 11 GW in 91 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 189 g CO₂ per kWh (California, 2025) Average of all power made in the area. Ember. |
| Grid power mix | solar 37.4%, gas 30.4%, hydro 11.7%, nuclear 7.3%, wind 6.7%. Clean power: 69.7% |
| Industrial power price | USD 0.241 per kWh (California, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 17.4 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 42.3 °C (2001 to 2025) |
| Cooling degree days | 778 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 5.78 kWh per m² per day |
| Wind at 50 m | 3.6 m/s average |
| Water stress today | Extremely High (>80%) (California) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Extremely High (>80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does CoreSite - Los Angeles (LA2) use?
We estimate the facility power at about 32 MW. Estimate from building footprint, low confidence.
How close is CoreSite - Los Angeles (LA2) to the power grid?
The nearest high-voltage substation in OpenStreetMap is Receiving Station A (230 kV), about 1.3 km away. The local utility is Los Angeles Department Of Water & Power, in the LDWP balancing area.
How clean is the power for CoreSite - Los Angeles (LA2)?
The grid in California emits about 189 g CO₂ per kWh (2025). Largest sources: solar 37.4%, gas 30.4%, hydro 11.7%.
Who operates CoreSite - Los Angeles (LA2)?
CoreSite.
Data centers near Los Angeles
- JMA NAC Los Angeles 2.1 km
- CoreSite - Los Angeles (LA1) One Wilshire 2.2 km · 45 MW
- MultaCom Main 2.2 km
- LADC5 - 650 S Grand Ave 2.3 km
- Telehouse - Los Angeles 2.3 km
- Psychz Networks LAX1 2.3 km
- Equinix LA1 - Los Angeles 2.3 km · 70 MW
- Equinix LA2 - Los Angeles 2.5 km
More CoreSite data centers
- CoreSite - Reston (VA3) United States
- CoreSite - Los Angeles (LA1) One Wilshire United States
- CoreSite - Denver (DE1) United States
- CoreSite - Reston (VA1) United States
- Coresite - Milpitas (SV2) United States
- CoreSite - Boston (BO1) United States
- CoreSite - Atlanta (AT2) United States
- CoreSite - Secaucus (NY2) United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.