Cyxtera Toronto YYZ2
Cyxtera Toronto YYZ2 is an operational data center operated by Cyxtera in Markham, Canada. Our footprint estimate of its power is about 19 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Cyxtera |
| Facility power | 19 MW (range 9.4 MW to 30 MW) Estimate from building footprint, low confidence. Footprint estimate: about 15,698 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 8,100 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | 14th Avenue 4175, L3R 0J2, Markham |
| Coordinates | 43.83827, -79.31674 |
Power and grid
| Nearest high-voltage substation | Parkway TS, 500 kV, 1.7 km away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 8 |
| Power plants within 50 km | 8.1 GW in 16 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 192 g CO₂ per kWh (Canada, 2025) Average of all power made in the area. Ember. |
| Grid power mix | hydro 52.8%, gas 19.7%, nuclear 12.8%, wind 8%, coal 2.7%. Clean power: 76.5% |
Climate and water
| Average temperature | 7.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 35.8 °C (2001 to 2025) |
| Cooling degree days | 307 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.62 kWh per m² per day |
| Wind at 50 m | 6.7 m/s average |
| Water stress today | Low - Medium (10-20%) (Ontario) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Cyxtera Toronto YYZ2 use?
We estimate the facility power at about 19 MW. Estimate from building footprint, low confidence.
How close is Cyxtera Toronto YYZ2 to the power grid?
The nearest high-voltage substation in OpenStreetMap is Parkway TS (500 kV), about 1.7 km away.
How clean is the power for Cyxtera Toronto YYZ2?
The grid in Canada emits about 192 g CO₂ per kWh (2025). Largest sources: hydro 52.8%, gas 19.7%, nuclear 12.8%.
Who operates Cyxtera Toronto YYZ2?
Cyxtera.
Data centers near Markham
- Centersquare Toronto (YYZ2) 99 m
- Digital Realty YYZ10 Toronto (371 Gough) 541 m · 14 MW
- Data center in Markham 626 m · 25 MW
- Equinix TR5 - Toronto 1.6 km · 12 MW
- Nuday DC1 1.9 km · 2.4 MW
- Rogers 2.5 km · 8.6 MW
- Cologix TOR4 2.5 km · 26 MW
- EdgeConneX Toronto (EDCTOR01) 3.8 km · 5.3 MW
More Cyxtera data centers
- Cyxtera (Digital Realty Trust) Citibank Data Center United States
- Cyxtera Toronto YYZ1 Canada
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.