Data Center
Data Center is an operational data center operated by Sabey Data Centers in Hennigsdorf, Germany. Our footprint estimate of its power is about 23 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Sabey Data Centers |
| Facility power | 23 MW (range 11 MW to 36 MW) Estimate from building footprint, low confidence. Footprint estimate: about 18,890 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 9,800 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | 52.62649, 13.22385 |
Power and grid
| Grid carbon intensity | 334 g CO₂ per kWh (Germany, 2025) Average of all power made in the area. Ember. |
|---|---|
| Grid power mix | wind 26.6%, coal 21%, solar 18%, gas 16.8%, bioenergy 10.1%. Clean power: 58.5% |
| Industrial power price | EUR 0.146 per kWh (Germany, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 9.7 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 37.7 °C (2001 to 2025) |
| Cooling degree days | 203 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.83 kWh per m² per day |
| Wind at 50 m | 6.5 m/s average |
| Water stress today | Medium - High (20-40%) (Brandenburg) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Data Center use?
We estimate the facility power at about 23 MW. Estimate from building footprint, low confidence.
How clean is the power for Data Center?
The grid in Germany emits about 334 g CO₂ per kWh (2025). Largest sources: wind 26.6%, coal 21%, solar 18%.
Who operates Data Center?
Sabey Data Centers.
Data centers near Hennigsdorf
- EXA Edge DC Velten 4.5 km
- NTT Berlin 1 Data Center (BER1) 9.8 km · 23 MW
- AtlasEdge DC Berlin BER001 12.7 km · 73 MW
- Aleph Alpha alpha ONE 14.5 km · 0.4 MW
- Pixelpark GmbH Colo II Berlin 17.0 km
- Rechenzentrum BER01 17.3 km · 4.6 MW
- Umspannwerk Berlin 20.2 km
- Speedbone Berlin 20.4 km · 0.9 MW
More Sabey Data Centers data centers
- Intergate.Quincy United States
- Intergate Columbia United States
- Sabey Intergate.Ashburn United States
- Intergate Seattle East Building 3 United States
- Intergate Columbia B United States
- Intergate West / Digital.forest / Fortress United States
- 375 Pearl, Intergate.Manhattan United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.