Equinix MI3 - Miami, Boca Raton
Equinix MI3 - Miami, Boca Raton is an operational data center operated by Equinix in Boca Raton, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Equinix |
| Networks | 15 networks, 2 internet exchanges PeeringDB. |
| Address | 4680 Conference Way South |
| Coordinates | 26.38799, -80.10827 |
| Website | equinix.com/locations/americas-colocation/united-states-colocation/miami-data-centers/mi3 |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 138 kV, 400 m away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Yamato Substation FPL, 230 kV, 2.7 km away |
| HV substations within 10 km | 18 |
| Utility | Florida Power & Light Co (investor owned) Electric retail service territory (HIFLD, US government). |
| Balancing authority | FPL |
| Nearest gas pipeline | Florida Gas Trans Co, interstate pipeline, 3.9 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 9.5 GW in 13 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 436 g CO₂ per kWh (Florida, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 71.7%, nuclear 11.2%, solar 11.1%, coal 3.7%, bioenergy 1.2%. Clean power: 23.6% |
| Industrial power price | USD 0.089 per kWh (Florida, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 24.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 33.6 °C (2001 to 2025) |
| Cooling degree days | 2,463 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 5.11 kWh per m² per day |
| Wind at 50 m | 5.6 m/s average |
| Water stress today | High (40-80%) (Florida) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | High (40-80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Equinix MI3 - Miami, Boca Raton to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (138 kV), about 400 m away. The local utility is Florida Power & Light Co, in the FPL balancing area.
How clean is the power for Equinix MI3 - Miami, Boca Raton?
The grid in Florida emits about 436 g CO₂ per kWh (2025). Largest sources: gas 71.7%, nuclear 11.2%, solar 11.1%.
Who operates Equinix MI3 - Miami, Boca Raton?
Equinix.
Data centers near Boca Raton
- Cogent Boca Raton 555 m
- Telxius Boca Raton DC 2.0 km
- Globenet Boca Raton CLS 5.2 km
- 500 Green (AKA VOLICO 2.0) 11.1 km
- Flexential - Fort Lauderdale (FLL1/2) 23.6 km · 6.5 MW
- 365 Data Centers Ft. Lauderdale (FLL) 24.0 km
- T-Mobile Everglades MSO Data Center 28.8 km · 4.9 MW
- EdgeConneX Miami (EDCMIA02) 49.9 km
More Equinix data centers
- Equinix DA1 - Dallas United States
- Equinix SP6 Brazil
- Equinix PH1 - Philadelphia United States
- Equinix PA13X France
- Equinix CH1/CH2/CH4 - Chicago United States
- Equinix CH3 - Elk Grove United States
- Equinix AM3 - Amsterdam, Science Park Netherlands
- Equinix LA1 - Los Angeles United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.