Google Fort Wayne

Google Fort Wayne is a data center under construction operated by Google in Fort Wayne, United States. No power figure is public for this site yet. Likely chips: Google TPU (plus NVIDIA GPUs for cloud customers) (guess).

Power demand is growing at this site

Key facts

StatusUnder construction
OperatorGoogle
UsersGoogle DeepMind (speculative)
Planned power1.0 GW by 2028-06-23
Epoch AI timeline projection.
AI chipsGoogle TPU (plus NVIDIA GPUs for cloud customers)
Guess from the operator, not confirmed. Google runs most of its AI work on its own TPU chips.
InvestorsGoogle
Address6015 Adams Center Road, Fort Wayne, IN 46806
Coordinates41.03093, -85.05363

Build timeline

DatePowerH100eWhat the satellite images and filings show
2024-04-0100First signs of development/land clearing
2024-09-1300Roof complete on Building 1 (the 'H'), although we suspect this building is not for AI compute due to the construction speed, irregular design, and lack of external cooling.
2025-06-1000After a long quiet period they've laid foundations for Building 2 and the substation.
2025-10-0100Building 2 looks externally complete
2026-03-0100The cooling towers for Buildings 2 and 3 are both a little less than half done and the buildings still look like active construction sites.
2026-08-1900Building 2 has all cooling towers installed and is likely undergoing fit-out and commissioning. So we give it about 3 more months until it's operational. Building 3 appears to be slightly further than Building 2 was in March, so we estimate a 4-month lag.
2026-12-01 (projected)207 MW383,000Estimated operational date of Building 2.
2027-03-31 (projected)414 MW824,000Estimated operational date of Building 3. Based on Building 3 construction looking about 4 months behind Building 2.
2027-08-28 (projected)621 MW1.4 millionEstimated operational date of Building 4. Based on Building 4 construction looking about 10 months behind Building 2.
2028-01-25 (projected)828 MW2.1 millionEstimated operational date of Building 5. Based on previous buildings being separated by about 5 months.
2028-06-23 (projected)1.0 GW2.9 millionEstimated operational date of Building 6. Based on previous buildings being separated by about 5 months.

Source: Epoch AI Frontier Data Centers.

Satellite view

Questions

What chips does Google Fort Wayne use?

No chips are reported. Based on the operator, the likely chips are Google TPU (plus NVIDIA GPUs for cloud customers).

Who operates Google Fort Wayne?

Google. Reported users: Google DeepMind.

More Google data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.