Iron Mountain Data Center - London (LON-1)
Iron Mountain Data Center - London (LON-1) is an operational data center operated by Iron Mountain in Slough, United Kingdom. Our footprint estimate of its power is about 28 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Iron Mountain |
| Facility power | 28 MW (range 14 MW to 44 MW) Estimate from building footprint, low confidence. Footprint estimate: about 23,008 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 12,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Networks | 7 networks PeeringDB. |
| Also known as | Iron Mountain London LON-1 |
| Address | 724-729 Dundee Road |
| Coordinates | 51.52733, -0.63110 |
| Website | ironmountain.com/digital-transformation/data-centers/locations/london-data-center |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 132 kV, 500 m away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Iver Substation, 400 kV, 9.4 km away |
| HV substations within 10 km | 11 |
| Power plants within 50 km | 3.8 GW in 97 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 218 g CO₂ per kWh (United Kingdom, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 31.3%, wind 29.4%, bioenergy 13.9%, nuclear 12.4%, solar 6.6%. Clean power: 64.2% |
Climate and water
| Average temperature | 10.3 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 34.9 °C (2001 to 2025) |
| Cooling degree days | 53 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.94 kWh per m² per day |
| Wind at 50 m | 7.1 m/s average |
| Water stress today | Low - Medium (10-20%) (England) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Iron Mountain Data Center - London (LON-1) use?
We estimate the facility power at about 28 MW. Estimate from building footprint, low confidence.
How close is Iron Mountain Data Center - London (LON-1) to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (132 kV), about 500 m away.
How clean is the power for Iron Mountain Data Center - London (LON-1)?
The grid in United Kingdom emits about 218 g CO₂ per kWh (2025). Largest sources: gas 31.3%, wind 29.4%, bioenergy 13.9%.
Who operates Iron Mountain Data Center - London (LON-1)?
Iron Mountain.
Data centers near Slough
- Equinix LD7 - London, Slough 273 m · 15 MW
- CyrusOne London 3 321 m · 7 MW
- Equinix LD4 - London, Slough 498 m · 11 MW
- Virgin Media O2 Slough 534 m · 8.4 MW
- Equinix LD5 - London, Slough 559 m · 21 MW
- Equinix LD6 - London, Slough 584 m · 4.6 MW
- CyrusOne London 1 687 m · 8.6 MW
- VIRTUS LONDON4 (Slough) 761 m
More Iron Mountain data centers
- Iron Mountain Data Center - New Jersey (NJE-1) United States
- Iron Mountain data center in Sandston United States
- Iron Mountain Data Center - Manassas (VA-1) United States
- Iron Mountain FRA-1 Germany
- Iron Mountain VA-3 United States
- Iron Mountain Data Center - Manassas (VA-2) United States
- Iron Mountain VA-7 United States
- Iron Mountain Australia
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.